up_reraStatus: Completed
CASE ID: 0901126044982022

Appellant / Complainant

Anshuman Jha

VS

Respondent

Agrani Homes Pvt Ltd

Developer Firm

agrani homes pvt ltd

Disposal Award

Unknown

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

27 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044982022 by Anshuman Jha against Agrani Homes Pvt Ltd before up_rera.

Non-Compliance & Execution
2
Stage 128/03/2024

for delivery of Judgment/Order

The Tribunal applied the order passed in EA No. 1946/2022 (Appeal No. 31/2021) to the instant case, effectively adopting previous rulings for this matter.

3
Stage 224/01/2024

Execution

The Tribunal refers the parties to a previously passed order dated in EA No. 1946/2022 (Appeal No. 31/2021) for further directions.

4
Stage 323/01/2024

Execution

The Tribunal directs that for the relevant orders, the parties should refer to the order previously passed in EA No. 1946/2022 (Appeal No. 31/2021).

5
Stage 419/10/2023

Execution

No text available.

6
Stage 513/09/2023

Execution

No text available.

7
Stage 625/07/2023

Execution

No text available.

8
Stage 717/07/2023

Execution

No text available.

9
Stage 804/05/2023

Execution

No text available.

10
Stage 923/03/2023

Execution

No text available.

11
Stage 1020/02/2023

Execution

No text available.

12
Stage 1118/01/2023

Execution

No text available.

13
Stage 1213/12/2022

Execution

No text available.

14
Stage 1325/11/2022

Execution

No text available.

15
Stage 1409/11/2022

Execution

No text available.

16
Stage 1518/10/2022

Execution

No text available.

17
Stage 1611/10/2022

Execution

No text available.

18
Stage 1730/09/2022

Execution

No text available.

19
Stage 1823/09/2022

Execution

No text available.

20
Stage 1912/09/2022

Execution

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must be approved by the Tribunal and conducted at or above circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

21
Stage 2030/08/2022

Execution

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate, Varanasi, to refrain from disposing of the builder's properties to prevent frustrating potential settlement or recovery efforts.

22
Stage 2116/08/2022

Execution

The Tribunal directed that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.

23
Stage 2208/08/2022

Execution

The Tribunal granted an adjournment requested by the respondent and rescheduled the hearing for August 16, 2022.

24
Stage 23Interim Order

Tribunal Order #0901126044982022-12-09-2022

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must be approved by the Tribunal and conducted at or above circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

25
Stage 24Interim Order

Tribunal Order #0901126044982022-30-08-2022

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate, Varanasi, to refrain from disposing of the builder's properties to prevent frustrating potential settlement or recovery efforts.

26
Stage 25Interim Order

Tribunal Order #0901126044982022-16-08-2022

The Tribunal directed that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.

Disposal Phase

Tribunal Disposal & Final Award Ruling

Unknown Awarded in favor of Unknown.

Disposal Winner: UnknownStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

Unknown

Ruling Awarded To

Unknown

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Arvind Kumar Shukla

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126044982022-12-09-2022

The Tribunal directed the judgment debtor to provide expressions of interest from joint venture partners and mandated that any asset sales must be approved by the Tribunal and conducted at or above circle rates, with proceeds deposited into an Escrow Account for proportionate distribution to decree holders.

INTERIM_ORDEROrder ID: 0901126044982022-30-08-2022

The Tribunal directed the judgment debtor to provide audited balance sheets and realistic asset valuations based on realizable value rather than future profit, and ordered the District Magistrate, Varanasi, to refrain from disposing of the builder's properties to prevent frustrating potential settlement or recovery efforts.

INTERIM_ORDEROrder ID: 0901126044982022-16-08-2022

The Tribunal directed that any funds recovered through the ongoing execution proceedings by the Regulatory Authority must be deposited into a specific Escrow Account at Indian Overseas Bank, Gomti Nagar Branch, Lucknow.