up_reraStatus: Completed
CASE ID: 0901126044622024

Appellant / Complainant

Shailaja Mishra, Sanjai Mishra

VS

Respondent

Royal Country Homes Pvt Ltd

Developer Firm

royal country homes pvt ltd

Disputed Amount

8,32,015

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

23 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044622024 by Shailaja Mishra, Sanjai Mishra against Royal Country Homes Pvt Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 124/02/2026

Hearing

The Tribunal dismissed the appeal, ruling that the respondent's construction on a single plot of less than 500 sq. mtrs. with fewer than eight units falls under the exemption clause of Section 3(2)(a) of the RERA Act, 2016, and thus does not require registration.

3
Stage 206/02/2026

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on 24.02.2026.

4
Stage 316/01/2026

Hearing

The Tribunal granted the appellant additional time to address the court on merits and scheduled the case for orders on February 6, 2026.

5
Stage 403/12/2025

Hearing

The Tribunal granted the respondent a final opportunity to file objections, warning that the matter will proceed ex-parte if they fail to do so, and rescheduled the hearing to 16.01.2026.

6
Stage 512/11/2025

For Order

The Tribunal granted the respondent a ten-day extension to file objections and scheduled the case for a final hearing on December 3, 2025.

7
Stage 617/10/2025

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for orders/hearing on 12.11.2025.

8
Stage 717/09/2025

For Order

The Tribunal noted compliance with substituted service via newspaper publication and granted the respondent 10 days to file objections, with the matter listed for hearing on 17.10.2025.

9
Stage 829/08/2025

For Order

The Tribunal allowed the appellant's application for substituted service of notice via publication in Hindi and English newspapers and scheduled the matter for 17.09.2025.

10
Stage 914/08/2025

For Order

The Tribunal granted a request for adjournment made by the appellant's counsel and scheduled the case for orders on 29.08.2025.

11
Stage 1028/07/2025

For Order

The Tribunal granted ten days to the appellant's counsel to file a substitution application and scheduled the next hearing for August 14, 2025.

12
Stage 1102/07/2025

For Order

The Tribunal granted a request by the appellant's counsel to reschedule the hearing of Appeal-438/2024 to 28.07.2025.

13
Stage 1228/04/2025

For Order

The Tribunal granted the appellant's counsel time to re-serve notice to the respondent and scheduled the appeal for hearing on July 2, 2025.

14
Stage 1301/04/2025

For Order

The court granted an adjournment application filed by the appellant's counsel and rescheduled the matter for hearing on 28.04.2025.

15
Stage 1405/03/2025

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for hearing on April 1, 2025.

16
Stage 1511/02/2025

For Order

The Tribunal allowed the appellant's application to implead the U.P. RERA, Lucknow, as a necessary party to the appeal and directed that notice be issued to them.

17
Stage 1616/01/2025

For Order

The Tribunal granted a request for adjournment and scheduled the appeal for a hearing on 11.02.2025, while directing that any objections to the amendment application be filed in the interim.

18
Stage 1716/12/2024

Admission

The Tribunal granted the appellant time to file an amendment application to bring a necessary party on record and scheduled the matter for orders on 16.01.2025.

19
Stage 1809/12/2024

Admission

The Tribunal granted the appellant time to remove registry defects and scheduled the appeal for orders/hearing on 16.12.2024.

20
Stage 19Final Ruling Order

Tribunal Order #0901126044622024-24-02-2026

The Tribunal dismissed the appeal, ruling that the respondent's construction on a single plot of less than 500 sq. mtrs. with fewer than eight units falls under the exemption clause of Section 3(2)(a) of the RERA Act, 2016, and thus does not require registration.

21
Stage 20Interim Order

Tribunal Order #0901126044622024-03-12-2025

The Tribunal granted the respondent a final opportunity to file objections, warning that the matter will proceed ex-parte if they fail to do so, and rescheduled the hearing to 16.01.2026.

22
Stage 21Interim Order

Tribunal Order #0901126044622024-11-02-2025

The Tribunal allowed the appellant's application to implead the U.P. RERA, Lucknow, as a necessary party to the appeal and directed that notice be issued to them.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed the appeal, ruling that the respondent's construction on a single plot of less than 500 sq. mtrs. with fewer than eight units falls under the exemption clause of Section 3(2)(a) of the RERA Act, 2016, and thus does not require registration. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed the appeal, ruling that the respondent's construction on a single plot of less than 500 sq. mtrs. with fewer than eight units falls under the exemption clause of Section 3(2)(a) of the RERA Act, 2016, and thus does not require registration.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Dwivedi

Respondent Advocate(s)

  • Jai Prakash Mishra

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126044622024-24-02-2026

The Tribunal dismissed the appeal, ruling that the respondent's construction on a single plot of less than 500 sq. mtrs. with fewer than eight units falls under the exemption clause of Section 3(2)(a) of the RERA Act, 2016, and thus does not require registration.

INTERIM_ORDEROrder ID: 0901126044622024-03-12-2025

The Tribunal granted the respondent a final opportunity to file objections, warning that the matter will proceed ex-parte if they fail to do so, and rescheduled the hearing to 16.01.2026.

INTERIM_ORDEROrder ID: 0901126044622024-11-02-2025

The Tribunal allowed the appellant's application to implead the U.P. RERA, Lucknow, as a necessary party to the appeal and directed that notice be issued to them.

TathyaGrid RERA Intelligence AI

Need to research all rulings for royal country homes pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →