Appellant / Complainant
U.P. Awas Evam Vikas Parishad
Respondent
Gan Nayak Pandey
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126044292024 by U.P. Awas Evam Vikas Parishad against Gan Nayak Pandey before up_rera.
Defect Removal
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to its failure to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.
Defect Removal
The Tribunal directed the Registry to verify the adequacy of the remaining deposit required under Section 43(5) of the RERA Act, 2016, following the appellant's undertaking to deposit the balance amount.
Delay condonation
The Tribunal granted the appellant a final opportunity to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, noting a shortfall between the Recovery Certificate amount and the amount already deposited.
Delay condonation
The Tribunal granted the appellant additional time to file calculations regarding Section 43(5) compliance and to seek further instructions, adjourning the matter to 20.11.2025.
Delay condonation
The Tribunal has directed the appellant to satisfy the mandate of Section 43 (5) of the Act 2016 and listed the appeal for orders/hearing on 04.11.2025.
Delay condonation
The Tribunal granted the respondent 10 days to file objections and directed that a rejoinder be filed within one week thereafter, scheduling the next hearing for 10.10.2025.
Delay condonation
The Tribunal granted the appellant seven days to file a rejoinder affidavit regarding objections to the delay condonation application and scheduled the next hearing for 18.09.2025.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent one-week deadline for the appellant to file a reply.
Tribunal Order #0901126044292024-15-12-2025
The Tribunal directed the Registry to verify the adequacy of the remaining deposit required under Section 43(5) of the RERA Act, 2016, following the appellant's undertaking to deposit the balance amount.
Tribunal Order #0901126044292024-22-01-2026
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to its failure to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.
Tribunal Order #0901126044292024-20-11-2025
The Tribunal granted the appellant a final opportunity to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, noting a shortfall between the Recovery Certificate amount and the amount already deposited.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to its failure to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to its failure to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
- Gautam Johri
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (3)
The Tribunal directed the Registry to verify the adequacy of the remaining deposit required under Section 43(5) of the RERA Act, 2016, following the appellant's undertaking to deposit the balance amount.
The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to its failure to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.
The Tribunal granted the appellant a final opportunity to comply with the mandatory deposit requirements under Section 43(5) of the Act, 2016, noting a shortfall between the Recovery Certificate amount and the amount already deposited.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.