up_reraStatus: Completed
CASE ID: 0901126044192021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Aman Chhibber

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044192021 by Lucknow Development Authority against Aman Chhibber before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

3
Stage 207/11/2022

For Order

The Tribunal noted that pleadings have been exchanged between the parties and has reserved the judgment for further consideration.

4
Stage 330/09/2022

For Order

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the defective appeal for hearing on 07.11.2022.

5
Stage 431/08/2022

Delay condonation

The Tribunal condoned the 68-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the registry to register the defective appeal as a regular appeal.

6
Stage 502/08/2022

Delay condonation

The Tribunal adjourned the appeal to 31.08.2022 due to the absence of the respondent.

7
Stage 626/05/2022

Hearing

The Tribunal directed the respondent to file a Vakalatnama and reply within two weeks and ordered both parties to upload their pleadings on the e-portal before the next hearing on 02.08.2022.

8
Stage 720/04/2022

Hearing

The Tribunal granted an adjournment requested by the applicant and directed the respondent's counsel to file an objection regarding the condonation of delay before the next hearing date.

9
Stage 803/03/2022

Hearing

The Tribunal granted an adjournment application filed by the counsel for the appellant and rescheduled the hearing of the defective appeal to 20.04.2022.

10
Stage 921/12/2021

Delay condonation

The Tribunal directed the appellant to take necessary steps to issue notice to the respondent within one week and scheduled the matter for consideration of the delay application on 20.01.2022.

11
Stage 1025/11/2021

Defect Removal

The Tribunal issued notice to the respondent via registered post and email and scheduled the case for 21.12.2021 to address the limitation application and objections.

12
Stage 11Final Ruling Order

Tribunal Order #0901126044192021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

13
Stage 12Interim Order

Tribunal Order #0901126044192021-31-08-2022

The Tribunal condoned the 68-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the registry to register the defective appeal as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Vinod Kumar Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126044192021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period (27.04.2013 to 26.10.2016) upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

INTERIM_ORDEROrder ID: 0901126044192021-31-08-2022

The Tribunal condoned the 68-day delay in filing the appeal due to COVID-19 pandemic relaxations and directed the registry to register the defective appeal as a regular appeal.