up_reraStatus: Completed
CASE ID: 0901126044182021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Balveer Prasad

Disputed Amount

49,50,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126044182021 by Lucknow Development Authority against Balveer Prasad before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/09/2022

for delivery of Judgment/Order

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to the respondent for delayed possession and directing the transfer of pre-deposited funds to the Regulatory Authority for disbursement.

3
Stage 223/08/2022

Further Order

The Tribunal heard arguments from the counsels for both parties and reserved the judgment for further pronouncement.

4
Stage 311/07/2022

Further Order

The Tribunal adjourned the case due to the absence of the respondent's counsel and scheduled the matter for a final hearing on 23.08.2022.

5
Stage 429/04/2022

Further Order

The Tribunal granted the appellant permission to file a replication against the respondent's reply within 10 days and scheduled the next hearing for July 11, 2022.

6
Stage 523/03/2022

Hearing

The Tribunal condoned a 65-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the registration of the defective appeal as a Regular Appeal.

7
Stage 610/01/2022

Delay condonation

The Tribunal granted an adjournment requested by the appellant's counsel due to illness and rescheduled the matter for February 8, 2022.

8
Stage 721/12/2021

Delay condonation

The Tribunal directed the respondent to file a Vakalatnama and an objection to the application for condonation of delay within specified timeframes, scheduling the matter for 10.01.2022.

9
Stage 825/11/2021

Defect Removal

The Tribunal issued a notice to the respondent via registered post and email and scheduled the case for 21.12.2021 to address the limitation application and any objections.

10
Stage 9Final Ruling Order

Tribunal Order #0901126044182021-30-09-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to the respondent for delayed possession and directing the transfer of pre-deposited funds to the Regulatory Authority for disbursement.

11
Stage 10Interim Order

Tribunal Order #0901126044182021-23-03-2022

The Tribunal condoned a 65-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the registration of the defective appeal as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to the respondent for delayed possession and directing the transfer of pre-deposited funds to the Regulatory Authority for disbursement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to the respondent for delayed possession and directing the transfer of pre-deposited funds to the Regulatory Authority for disbursement.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 14.09.2014 to 18.08.2020 (excluding the period of two years)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Yadav

Respondent Advocate(s)

  • Mohd. Yasir Abbasi
  • Sharad Kumar Shukla

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126044182021-30-09-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority, upholding the Adjudicating Officer's order to pay interest/compensation to the respondent for delayed possession and directing the transfer of pre-deposited funds to the Regulatory Authority for disbursement.

INTERIM_ORDEROrder ID: 0901126044182021-23-03-2022

The Tribunal condoned a 65-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the registration of the defective appeal as a Regular Appeal.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →