Appellant / Complainant
Abha Khanna
Respondent
K.V.G. Pvt Ltd
k.v.g. pvt ltd
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126043542024 by Abha Khanna against K.V.G. Pvt Ltd before up_rera.
for delivery of Judgment/Order
The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.
For Order
The Tribunal heard ex-parte arguments from the appellant's counsel regarding a review application and reserved the order for judgment.
For Order
The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.
For Order
The Tribunal granted the respondent 10 days to file their Vakalatnama and objections, with a directive for the appellant to reply within one week thereafter, and scheduled the next hearing for August 6, 2025.
For Order
The Tribunal granted the respondent time to file a Vakalatnama and objections, adjourning the matter to July 16, 2025.
For Order
The Tribunal granted a request from the appellant's counsel to reschedule the hearing of RP-15/2024 to 27.05.2022 before an appropriate Bench.
For Order
The Tribunal issued fresh notice to the respondent due to previous non-service and directed the applicant to serve the application via speed-post and email, with the matter listed for 02.05.2025.
For Order
The Tribunal directed the appellant to file an affidavit of service and scheduled the case for orders on April 9, 2025.
For Order
Due to a strike by the Bar Council of Uttar Pradesh, the tribunal has adjourned the matter and scheduled the hearing for March 27, 2025.
For Order
The Tribunal has ordered the matter to be listed before the appropriate Bench on February 25, 2025.
For Order
The Tribunal noted the absence of both parties and adjourned the matter to 18.02.2025 for hearing.
For Order
The Tribunal has adjourned the review petition (RP-15/2024) to 24.01.2025 to allow the respondent's counsel to file objections.
For Order
The Tribunal granted the respondent 10 days to file an objection to the review petition and scheduled the matter for hearing on January 7, 2025.
Tribunal Order #0901126043542024-06-08-2025
The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.
Tribunal Order #0901126043542024-20-11-2025
The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.
Tribunal Disposal & Final Award Ruling
The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% of SBI.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1% of SBI
Interest Period
from 30.07.2018 till the date of delivery of actual possession along with OC/CC
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Vasudev Trivedi
- Abhishek Khare
Respondent Advocate(s)
- Mahendra Singh
Official RERA Tribunal Orders (2)
The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.
The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.