up_reraStatus: Completed
CASE ID: 0901126043542024

Appellant / Complainant

Abha Khanna

VS

Respondent

K.V.G. Pvt Ltd

Developer Firm

k.v.g. pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126043542024 by Abha Khanna against K.V.G. Pvt Ltd before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 120/11/2025

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.

3
Stage 225/08/2025

For Order

The Tribunal heard ex-parte arguments from the appellant's counsel regarding a review application and reserved the order for judgment.

4
Stage 306/08/2025

For Order

The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.

5
Stage 416/07/2025

For Order

The Tribunal granted the respondent 10 days to file their Vakalatnama and objections, with a directive for the appellant to reply within one week thereafter, and scheduled the next hearing for August 6, 2025.

6
Stage 527/05/2025

For Order

The Tribunal granted the respondent time to file a Vakalatnama and objections, adjourning the matter to July 16, 2025.

7
Stage 602/05/2025

For Order

The Tribunal granted a request from the appellant's counsel to reschedule the hearing of RP-15/2024 to 27.05.2022 before an appropriate Bench.

8
Stage 709/04/2025

For Order

The Tribunal issued fresh notice to the respondent due to previous non-service and directed the applicant to serve the application via speed-post and email, with the matter listed for 02.05.2025.

9
Stage 827/03/2025

For Order

The Tribunal directed the appellant to file an affidavit of service and scheduled the case for orders on April 9, 2025.

10
Stage 925/02/2025

For Order

Due to a strike by the Bar Council of Uttar Pradesh, the tribunal has adjourned the matter and scheduled the hearing for March 27, 2025.

11
Stage 1018/02/2025

For Order

The Tribunal has ordered the matter to be listed before the appropriate Bench on February 25, 2025.

12
Stage 1124/01/2025

For Order

The Tribunal noted the absence of both parties and adjourned the matter to 18.02.2025 for hearing.

13
Stage 1207/01/2025

For Order

The Tribunal has adjourned the review petition (RP-15/2024) to 24.01.2025 to allow the respondent's counsel to file objections.

14
Stage 1323/11/2024

For Order

The Tribunal granted the respondent 10 days to file an objection to the review petition and scheduled the matter for hearing on January 7, 2025.

15
Stage 14Interim Order

Tribunal Order #0901126043542024-06-08-2025

The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.

16
Stage 15Final Ruling Order

Tribunal Order #0901126043542024-20-11-2025

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% of SBI.

Disposal Winner: RespondentInterest Rate: MCLR+1% of SBIStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% of SBI

Interest Period

from 30.07.2018 till the date of delivery of actual possession along with OC/CC

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vasudev Trivedi
  • Abhishek Khare

Respondent Advocate(s)

  • Mahendra Singh

Official RERA Tribunal Orders (2)

INTERIM_ORDEROrder ID: 0901126043542024-06-08-2025

The Tribunal has decided to proceed ex-parte against the respondent, M/S KVG Realtech Pvt. Ltd., due to their repeated failure to file a vakalatnama or objections despite multiple opportunities.

FINAL_ORDEROrder ID: 0901126043542024-20-11-2025

The Uttar Pradesh Real Estate Appellate Tribunal rejected the review petition filed by Abha Khanna, maintaining its previous decision that delay interest is payable from 30.07.2018 rather than the date of agreement.

TathyaGrid RERA Intelligence AI