Appellant / Complainant
Ansal Properties & Infrastructure Limited
Respondent
Uttar Pradesh Real Estate Regulatory Authority
ansal properties & infrastructure limited
Unknown
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126043502021 by Ansal Properties & Infrastructure Limited against Uttar Pradesh Real Estate Regulatory Authority before up_rera.
Hearing
The Tribunal refers to a previously passed order dated 04.02.2025 in Appeal No. 629/2021 regarding the matter of Ansal API Vs. UP RERA.
Hearing
The Tribunal noted the filing of a resolution proposal by the appellant and, upon joint request of the counsel, adjourned the matter for hearing on 04.02.2025.
Hearing
The Tribunal has rescheduled the hearing of Appeal-761/2021 to 17.01.2025 following a joint request from the counsels for both parties.
Hearing
The Tribunal directed the appellant to comply with the order dated 22.10.2024 and submit a proposal or resolution for the completion of the project, while adjourning the matter to 06.12.2024.
Hearing
The Tribunal directed the appellant to submit a formal resolution proposal detailing the funds required for project completion and the specific arrangements for securing those funds.
Hearing
The appellant sought an adjournment, which was granted without objection from the respondent; the matter is rescheduled for hearing on 22.10.2024.
Hearing
The Tribunal granted a request for adjournment due to personal grounds and rescheduled the appeal for hearing on 20.09.2024.
Hearing
The Tribunal granted a request from the respondent's counsel to adjourn the matter and rescheduled the appeal for orders to 20.08.2024.
For Order
The Tribunal adjourned the proceedings of Appeal-761/2021 due to the absence of the appellant's counsel and scheduled the matter for hearing on 09.08.2024.
For Order
The Tribunal directed that this appeal be listed before a different Bench, following the order passed in Appeal No. 335 of 2021.
For Order
The Tribunal ordered the case to be kept in abeyance due to a moratorium issued by the NCLT on 16.11.2022 affecting the appellant.
For Order
The Tribunal directed the Registry to summon the records from the lower authority to facilitate a fair decision and scheduled the next hearing for December 1, 2022.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel due to personal difficulties and rescheduled the matter for hearing on 02.11.2022.
For Order
The Tribunal allowed an application to condone a 37-day delay in filing an affidavit and directed the respondent to rectify defects in their consolidation application before listing the matter for hearing on 17.10.2022.
Hearing
The Tribunal granted the appellant a one-week extension to file an application for condonation of delay regarding the late submission of an affidavit.
Hearing
The Tribunal has ordered the appeal to be listed for a hearing on 22.09.2022.
Hearing
The Tribunal granted the appellant two weeks' time to file documents regarding the project's physical and financial progress and scheduled the next hearing for September 1, 2022.
Hearing
The Tribunal granted an adjournment requested by the appellant due to personal exigency and directed that Appeal Nos. 628/2021 and 629/2021 be listed together with this appeal for a hearing on 01.08.2022.
Hearing
The court granted a request for adjournment due to a personal emergency involving the respondent's counsel and rescheduled the hearing to 22.07.2022.
Hearing
The Tribunal granted an adjournment requested by the respondent's counsel due to the senior counsel's unavailability and scheduled the matter for further orders on 13.07.2022.
Hearing
The Tribunal noted that the appellant has filed a replication/rejoinder on the e-portal and scheduled the appeal for hearing on 31.05.2022.
Hearing
The Tribunal granted the appellant a final opportunity to file a replication against the respondent's reply and scheduled the case for hearing on 05.05.2022.
Hearing
The Tribunal granted the appellant permission to file a rejoinder/replication to the respondent's reply and adjourned the matter to 21.04.2022.
Hearing
The Tribunal noted that the respondent has filed a reply and served it via email; the matter is adjourned to 28.03.2022 for hearing.
Hearing
The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and directed both parties to exchange pleadings via email and upload them to the e-portal before the next hearing on 17.01.2022.
Hearing
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 regarding COVID-19 limitations, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126043502021-05-11-2024
The Tribunal directed the appellant to comply with the order dated 22.10.2024 and submit a proposal or resolution for the completion of the project, while adjourning the matter to 06.12.2024.
Tribunal Order #0901126043502021-01-12-2022
The Tribunal ordered the case to be kept in abeyance due to a moratorium issued by the NCLT on 16.11.2022 affecting the appellant.
Tribunal Order #0901126043502021-11-11-2021
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 regarding COVID-19 limitations, and directed the Registry to convert the defective appeal into a regular appeal.
Tribunal Order #0901126043502021-22-10-2024
The Tribunal directed the appellant to submit a formal resolution proposal detailing the funds required for project completion and the specific arrangements for securing those funds.
Tribunal Disposal & Final Award Ruling
Unknown Awarded in favor of Unknown.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Unknown
Ruling Awarded To
Unknown
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
Respondent Advocate(s)
- Shobhit Mohan Shukla
Official RERA Tribunal Orders (4)
The Tribunal directed the appellant to comply with the order dated 22.10.2024 and submit a proposal or resolution for the completion of the project, while adjourning the matter to 06.12.2024.
The Tribunal ordered the case to be kept in abeyance due to a moratorium issued by the NCLT on 16.11.2022 affecting the appellant.
The Tribunal condoned the delay in filing the appeal, citing the Supreme Court's Suo Motu Writ Petition (Civil) No. 3 of 2020 regarding COVID-19 limitations, and directed the Registry to convert the defective appeal into a regular appeal.
The Tribunal directed the appellant to submit a formal resolution proposal detailing the funds required for project completion and the specific arrangements for securing those funds.