up_reraStatus: Completed
CASE ID: 0901126043492021

Appellant / Complainant

Sudhanshu Tripathi

VS

Respondent

Kanchhal Group Lucknow(Manya Infrabuildwell Pvt Lt

Developer Firm

manya infrabuildwell pvt ltd

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Jurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

6 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126043492021 by Sudhanshu Tripathi against Kanchhal Group Lucknow(Manya Infrabuildwell Pvt Lt before up_rera.

Jurisdiction & Maintainability
2
Stage 107/03/2022

Notice

The U.P. Real Estate Appellate Tribunal dismissed the appeal because the respondent's project was not registered under Section 3 of the RERA Act 2016, making the complaint and appeal non-maintainable pursuant to Supreme Court precedent.

3
Stage 203/01/2022

Notice

The Tribunal directed the appellant's counsel to take necessary steps within one week following a failure to comply with previous orders and scheduled the matter for further proceedings on 24.01.2022.

4
Stage 329/11/2021

Defect Removal

The Tribunal noted that the appeal was filed within time and directed that notice be issued to the respondents via registered post and email, with the case listed for 03.01.2022.

5
Stage 4Final Ruling Order

Tribunal Order #0901126043492021-07-03-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal because the respondent's project was not registered under Section 3 of the RERA Act 2016, making the complaint and appeal non-maintainable pursuant to Supreme Court precedent.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal because the respondent's project was not registered under Section 3 of the RERA Act 2016, making the complaint and appeal non-maintainable pursuant to Supreme Court precedent. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal because the respondent's project was not registered under Section 3 of the RERA Act 2016, making the complaint and appeal non-maintainable pursuant to Supreme Court precedent.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Jayendra Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126043492021-07-03-2022

The U.P. Real Estate Appellate Tribunal dismissed the appeal because the respondent's project was not registered under Section 3 of the RERA Act 2016, making the complaint and appeal non-maintainable pursuant to Supreme Court precedent.

TathyaGrid RERA Intelligence AI

Need to research all rulings for manya infrabuildwell pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →