up_reraStatus: Completed
CASE ID: 0901126043052023

Appellant / Complainant

Uppal Chadha Hi-Tech Developers Pvt. Ltd.

VS

Respondent

Annu Agrawal

Developer Firm

uppal chadha hi-tech developers pvt. ltd.

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126043052023 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Annu Agrawal before up_rera.

2
Stage 107/07/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay, dismissed the appeal due to lack of sufficient cause, and ordered the transfer of the deposited amount to the Regulatory Authority.

3
Stage 203/04/2025

Delay condonation

The appeal was dismissed for non-prosecution due to the absence of the appellant, and the court directed that the amount deposited under Section 43(5) of the Act 2016 be released to the respondent as per law.

4
Stage 310/03/2025

Delay condonation

The Tribunal granted the respondent two weeks to file objections and directed the appellant to file a reply within one week thereafter, scheduling the next hearing for April 3, 2025.

5
Stage 413/02/2025

Delay condonation

The Tribunal has adjourned the appeal to 10.03.2025 and directed that pleadings be completed in the interim.

6
Stage 513/01/2025

Delay condonation

No text available.

7
Stage 609/12/2024

Delay condonation

The Tribunal issued notice to the respondent regarding the appeal and the delay condonation application, scheduling the next hearing for January 13, 2025.

8
Stage 7Final Ruling Order

Tribunal Order #0901126043052023-07-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay, dismissed the appeal due to lack of sufficient cause, and ordered the transfer of the deposited amount to the Regulatory Authority.

9
Stage 8Final Ruling Order

Tribunal Order #0901126043052023-03-04-2025

The appeal was dismissed for non-prosecution due to the absence of the appellant, and the court directed that the amount deposited under Section 43(5) of the Act 2016 be released to the respondent as per law.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay, dismissed the appeal due to lack of sufficient cause, and ordered the transfer of the deposited amount to the Regulatory Authority. The appeal was dismissed for non-prosecution due to the absence of the appellant, and the court directed that the amount deposited under Section 43(5) of the Act 2016 be released to the respondent as per law. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay, dismissed the appeal due to lack of sufficient cause, and ordered the transfer of the deposited amount to the Regulatory Authority. The appeal was dismissed for non-prosecution due to the absence of the appellant, and the court directed that the amount deposited under Section 43(5) of the Act 2016 be released to the respondent as per law.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Surangama Sharma

Respondent Advocate(s)

  • Abhishek Shukla

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126043052023-07-07-2025

The U.P. Real Estate Appellate Tribunal rejected the appellant's application for condonation of delay, dismissed the appeal due to lack of sufficient cause, and ordered the transfer of the deposited amount to the Regulatory Authority.

FINAL_ORDEROrder ID: 0901126043052023-03-04-2025

The appeal was dismissed for non-prosecution due to the absence of the appellant, and the court directed that the amount deposited under Section 43(5) of the Act 2016 be released to the respondent as per law.

TathyaGrid RERA Intelligence AI

Need to research all rulings for uppal chadha hi-tech developers pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →