up_reraStatus: Completed
CASE ID: 0901126042592022

Appellant / Complainant

Harmeet Arora

VS

Respondent

Maheshwari Infratech Private Limited

Developer Firm

maheshwari infratech private limited

Disputed Amount

22,62,028

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126042592022 by Harmeet Arora against Maheshwari Infratech Private Limited before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestUnfair Cancellation & Forfeiture
2
Stage 109/12/2022

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.

3
Stage 211/11/2022

Further Hearing

The Tribunal has heard the arguments from both parties and has reserved the judgment for a later date.

4
Stage 309/11/2022

For Order

The Tribunal granted an adjournment to the appellant upon request for more time to prepare their brief and rescheduled the hearing for 11.11.2022.

5
Stage 429/09/2022

For Order

The Tribunal noted that the respondent had filed objections and the appellant declined to file a reply; consequently, the matter was adjourned to 09.11.2022.

6
Stage 502/09/2022

Notice

The Tribunal ruled that service of notice upon the respondent was sufficient via post and email, granting the respondent 10 days to file objections before the matter proceeds ex parte.

7
Stage 604/08/2022

Hearing on Appeal

The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.

8
Stage 7Final Ruling Order

Tribunal Order #0901126042592022-09-12-2022

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.

9
Stage 8Interim Order

Tribunal Order #0901126042592022-04-08-2022

The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(5)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Padmanabh Tiwari
  • Ved Prakash Mishra

Respondent Advocate(s)

  • Suchita Singh

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126042592022-09-12-2022

The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.

INTERIM_ORDEROrder ID: 0901126042592022-04-08-2022

The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.

TathyaGrid RERA Intelligence AI

Need to research all rulings for maheshwari infratech private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →