Appellant / Complainant
Harmeet Arora
Respondent
Maheshwari Infratech Private Limited
maheshwari infratech private limited
₹22,62,028
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126042592022 by Harmeet Arora against Maheshwari Infratech Private Limited before up_rera.
for delivery of Judgment/Order
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.
Further Hearing
The Tribunal has heard the arguments from both parties and has reserved the judgment for a later date.
For Order
The Tribunal granted an adjournment to the appellant upon request for more time to prepare their brief and rescheduled the hearing for 11.11.2022.
For Order
The Tribunal noted that the respondent had filed objections and the appellant declined to file a reply; consequently, the matter was adjourned to 09.11.2022.
Notice
The Tribunal ruled that service of notice upon the respondent was sufficient via post and email, granting the respondent 10 days to file objections before the matter proceeds ex parte.
Hearing on Appeal
The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.
Tribunal Order #0901126042592022-09-12-2022
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.
Tribunal Order #0901126042592022-04-08-2022
The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.
Tribunal Disposal & Final Award Ruling
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Padmanabh Tiwari
- Ved Prakash Mishra
Respondent Advocate(s)
- Suchita Singh
Official RERA Tribunal Orders (2)
The Appellate Tribunal dismissed the appeal, upholding the Regulatory Authority's order that allowed the respondent to forfeit the earnest money (15% of total cost) due to the appellant's failure to pay installments as per the Builder Buyer Agreement.
The Tribunal issued notice to the respondent and directed the appellant to produce the complete brochure, allotment letter, and all payment demand documents related to construction milestones within one week.
Need to research all rulings for maheshwari infratech private limited?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.