Appellant / Complainant
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Respondent
Anita Gupta
uppal chadha hi-tech developers pvt. ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126042572022 by Uppal Chadha Hi-Tech Developers Pvt. Ltd. against Anita Gupta before up_rera.
Delay condonation
The Tribunal rejected the application for condonation of delay due to a lack of plausible explanation and consequently dismissed Appeal No. 714/2023.
Delay condonation
The court noted that advocates are abstaining from judicial work due to a Bar Council resolution and has rescheduled the case for orders on 04.12.2024.
Delay condonation
The Tribunal has adjourned the appeal to 04.11.2024 for hearing upon the mutual request of both counsels.
Delay condonation
The Tribunal has scheduled the hearing for the application for condonation of delay and the consideration of the defective appeal for September 23, 2024, following a joint request from both counsels.
Delay condonation
The Tribunal granted the appellant seven days to upload a rejoinder affidavit due to technical issues and scheduled the matter for hearing on August 27, 2024.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objection and scheduled the matter for July 30, 2024, to consider an application for condonation of delay.
Delay condonation
The Tribunal granted the appellant one week to file a reply to the respondent's objections and scheduled the matter for July 3, 2024, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and grounds of appeal, scheduling the matter for hearing on May 3, 2024.
Delay condonation
The Tribunal granted a final 10-day extension to the respondent to file objections regarding the condonation of delay and grounds of appeal, warning that failure to comply will result in the matter proceeding ex-parte.
Delay condonation
The Tribunal acknowledged sufficient service of notice on the respondent but granted a 10-day extension for filing objections in the interest of justice.
Defect Removal
The Tribunal provisionally accepted the appellant's deposit of Rs. 8,81,799/- in compliance with Section 43(5) and issued notice to the respondent regarding an application for condonation of a 62-day delay.
Tribunal Order #0901126042572022-04-12-2024
The Tribunal rejected the application for condonation of delay due to a lack of plausible explanation and consequently dismissed Appeal No. 714/2023.
Tribunal Order #0901126042572022-28-02-2024
The Tribunal granted a final 10-day extension to the respondent to file objections regarding the condonation of delay and grounds of appeal, warning that failure to comply will result in the matter proceeding ex-parte.
Tribunal Order #0901126042572022-20-12-2023
The Tribunal provisionally accepted the appellant's deposit of Rs. 8,81,799/- in compliance with Section 43(5) and issued notice to the respondent regarding an application for condonation of a 62-day delay.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the application for condonation of delay due to a lack of plausible explanation and consequently dismissed Appeal No. 714/2023. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the application for condonation of delay due to a lack of plausible explanation and consequently dismissed Appeal No. 714/2023.
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Bal Kishor Verma
- Amit Yadav
Respondent Advocate(s)
- Suchita Singh
Official RERA Tribunal Orders (3)
The Tribunal rejected the application for condonation of delay due to a lack of plausible explanation and consequently dismissed Appeal No. 714/2023.
The Tribunal granted a final 10-day extension to the respondent to file objections regarding the condonation of delay and grounds of appeal, warning that failure to comply will result in the matter proceeding ex-parte.
The Tribunal provisionally accepted the appellant's deposit of Rs. 8,81,799/- in compliance with Section 43(5) and issued notice to the respondent regarding an application for condonation of a 62-day delay.