up_reraStatus: Completed
CASE ID: 0901126041732024

Appellant / Complainant

Domus Greens Private Limited

VS

Respondent

Mohini Tripathi, Rohit Tripathi

Developer Firm

domus greens private limited

Disputed Amount

59,78,261

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126041732024 by Domus Greens Private Limited against Mohini Tripathi, Rohit Tripathi before up_rera.

2
Stage 118/04/2025

Delay condonation

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with the court directing the distribution of the deposited Rs. 59,78,261/- and its accrued interest between the appellant-promoter and respondent-allottee.

3
Stage 221/03/2025

Delay condonation

Upon the joint request of both parties, the Tribunal has adjourned the appeal and scheduled it for orders/hearing on 18.04.2025.

4
Stage 320/02/2025

Delay condonation

The Tribunal modified its previous order to allow the appellant to seek the release of Rs. 30 lakh from the Regulatory Authority, as the decretal amount has been fully satisfied, and granted liberty to de-freeze the appellant's bank account following such release.

5
Stage 417/02/2025

Delay condonation

The Tribunal scheduled the appeal for hearing on 20.02.2025 and directed that an application for the de-freezing of the appellant's bank accounts will be considered on that date.

6
Stage 507/02/2025

Delay condonation

The Tribunal directed the respondent to serve objections to the delay condonation application and ordered the appellant to file a rejoinder within one week, scheduling the next hearing for 17.02.2025.

7
Stage 606/01/2025

Delay condonation

The Tribunal issued notice to the respondents regarding the application for condonation of delay and directed the appellant to serve the notice and appeal documents via post and email.

8
Stage 7Interim Order

Tribunal Order #0901126041732024-20-02-2025

The Tribunal modified its previous order to allow the appellant to seek the release of Rs. 30 lakh from the Regulatory Authority, as the decretal amount has been fully satisfied, and granted liberty to de-freeze the appellant's bank account following such release.

9
Stage 8Final Ruling Order

Tribunal Order #0901126041732024-18-04-2025

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with the court directing the distribution of the deposited Rs. 59,78,261/- and its accrued interest between the appellant-promoter and respondent-allottee.

10
Stage 9Interim Order

Tribunal Order #0901126041732024-17-02-2025

The Tribunal scheduled the appeal for hearing on 20.02.2025 and directed that an application for the de-freezing of the appellant's bank accounts will be considered on that date.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with the court directing the distribution of the deposited Rs. 59,78,261/- and its accrued interest between the appellant-promoter and respondent-allottee. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with the court directing the distribution of the deposited Rs. 59,78,261/- and its accrued interest between the appellant-promoter and respondent-allottee.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Amit Kumar Singh

Respondent Advocate(s)

  • Sunendra Kumar
  • Sunendra Kumar Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126041732024-20-02-2025

The Tribunal modified its previous order to allow the appellant to seek the release of Rs. 30 lakh from the Regulatory Authority, as the decretal amount has been fully satisfied, and granted liberty to de-freeze the appellant's bank account following such release.

FINAL_ORDEROrder ID: 0901126041732024-18-04-2025

The appeal was dismissed as withdrawn following an amicable settlement between the parties, with the court directing the distribution of the deposited Rs. 59,78,261/- and its accrued interest between the appellant-promoter and respondent-allottee.

INTERIM_ORDEROrder ID: 0901126041732024-17-02-2025

The Tribunal scheduled the appeal for hearing on 20.02.2025 and directed that an application for the de-freezing of the appellant's bank accounts will be considered on that date.

TathyaGrid RERA Intelligence AI

Need to research all rulings for domus greens private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →