Appellant / Complainant
U.P. State Industrial Development Corporation Ltd. And Another
Respondent
Syed Mahboob Ahmad
u.p. state industrial development corporation ltd.
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126041312023 by U.P. State Industrial Development Corporation Ltd. And Another against Syed Mahboob Ahmad before up_rera.
For Order
The Tribunal rejected the appellant's application (IA No. 2663 of 2023) for the release of accrued interest, noting that the principal amount had already been transferred to U.P.RERA and released to the respondent in previous execution proceedings.
For Order
The Tribunal granted a one-week extension to the appellant (UPSIDC) to file objections regarding the respondent's application for the release of funds deposited under Section 43(5) of the Act, rescheduling the hearing to April 2, 2024.
For Order
The Tribunal granted the Appellant one week's time to file objections regarding the Respondent's application for the release of funds deposited under Section 43(5) of the Act and scheduled the matter for hearing on 28.02.2024.
For Order
The Tribunal has scheduled the application for consideration regarding the release of funds deposited under Section 43(5) of the Act for February 21, 2024.
For Order
The Tribunal adjourned the proceedings because the respondent, Syed Mahboob Ahmad, was not present, and rescheduled the case for consideration on 31.10.2023.
For Order
The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the application for hearing on 18.09.2023.
For Order
The Tribunal adjourned the proceedings due to a three-day strike called by the Bar Council of Uttar Pradesh and rescheduled the application for hearing on 11.09.2023.
Tribunal Disposal & Final Award Ruling
Rejected Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Rejected
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Need to research all rulings for u.p. state industrial development corporation ltd.?