up_reraStatus: Completed
CASE ID: 0901126040912024

Appellant / Complainant

Patel Advance Jv

VS

Respondent

Dheeraj Koul

Developer Firm

patel advance jv

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126040912024 by Patel Advance Jv against Dheeraj Koul before up_rera.

Non-Compliance & Execution
2
Stage 126/08/2025

Hearing

The Tribunal disposed of the appeal by directing the UP RERA Executing Authority to expedite and conclude the execution proceedings related to the 2019 judgment, preferably within twelve weeks.

3
Stage 206/08/2025

Hearing

The Tribunal has restrained the appellant from creating any third-party rights or interests or charges on the unit that is the subject matter of the appeal.

4
Stage 328/07/2025

Hearing

The Tribunal granted a request from the respondent's counsel to list the case for orders or hearing on 06.08.2025 and permitted the filing of replies or objections to documents submitted today.

5
Stage 403/07/2025

Hearing

The Tribunal directed the appellant to bring on record the completion status of the project, including OC/CC documents, NOCs, and the current physical status and validity of construction permits.

6
Stage 505/05/2025

Hearing

The appeal has been adjourned at the request of the appellant's counsel and is scheduled for orders/hearing on 03.07.2025.

7
Stage 609/04/2025

Hearing

The Tribunal granted a request from the respondent's counsel to adjourn the hearing to 05.05.2025, with any existing interim orders to remain in effect until the next listing.

8
Stage 717/03/2025

For Order

The Tribunal has scheduled the case for orders on 09.04.2025 and extended any existing interim orders until the next listing date.

9
Stage 817/02/2025

For Order

The Tribunal adjourned the appeal to 17.03.2025 and directed the appellant to upload the revenue authority receipt verifying the deposit amount by the next hearing date.

10
Stage 923/01/2025

For Order

The Tribunal adjourned the appeal to 17.02.2025 and directed the appellant to file a rejoinder and the respondent to upload any outstanding demands.

11
Stage 1020/12/2024

Admission

The Tribunal granted interim relief by keeping the operation of the impugned order dated 19.09.2024 in abeyance due to the appellant's prior deposit of principal and interest. The matter is scheduled for hearing on the application for condonation of delay on 23.01.2025.

12
Stage 11Interim Order

Tribunal Order #0901126040912024-06-08-2025

The Tribunal has restrained the appellant from creating any third-party rights or interests or charges on the unit that is the subject matter of the appeal.

13
Stage 12Interim Order

Tribunal Order #0901126040912024-20-12-2024

The Tribunal granted interim relief by keeping the operation of the impugned order dated 19.09.2024 in abeyance due to the appellant's prior deposit of principal and interest. The matter is scheduled for hearing on the application for condonation of delay on 23.01.2025.

14
Stage 13Final Ruling Order

Tribunal Order #0901126040912024-26-08-2025

The Tribunal disposed of the appeal by directing the UP RERA Executing Authority to expedite and conclude the execution proceedings related to the 2019 judgment, preferably within twelve weeks.

15
Stage 14Interim Order

Tribunal Order #0901126040912024-03-07-2025

The Tribunal directed the appellant to bring on record the completion status of the project, including OC/CC documents, NOCs, and the current physical status and validity of construction permits.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal disposed of the appeal by directing the UP RERA Executing Authority to expedite and conclude the execution proceedings related to the 2019 judgment, preferably within twelve weeks. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal disposed of the appeal by directing the UP RERA Executing Authority to expedite and conclude the execution proceedings related to the 2019 judgment, preferably within twelve weeks.

Ruling Awarded To

Partial

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Rohit Jaiswal
  • Jayant Gupta

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (4)

INTERIM_ORDEROrder ID: 0901126040912024-06-08-2025

The Tribunal has restrained the appellant from creating any third-party rights or interests or charges on the unit that is the subject matter of the appeal.

INTERIM_ORDEROrder ID: 0901126040912024-20-12-2024

The Tribunal granted interim relief by keeping the operation of the impugned order dated 19.09.2024 in abeyance due to the appellant's prior deposit of principal and interest. The matter is scheduled for hearing on the application for condonation of delay on 23.01.2025.

FINAL_ORDEROrder ID: 0901126040912024-26-08-2025

The Tribunal disposed of the appeal by directing the UP RERA Executing Authority to expedite and conclude the execution proceedings related to the 2019 judgment, preferably within twelve weeks.

INTERIM_ORDEROrder ID: 0901126040912024-03-07-2025

The Tribunal directed the appellant to bring on record the completion status of the project, including OC/CC documents, NOCs, and the current physical status and validity of construction permits.