up_reraStatus: Completed
CASE ID: 0901126040352024

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Anil Kumar Tiwari

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

13 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126040352024 by U.P. Awas Evam Vikas Parishad against Anil Kumar Tiwari before up_rera.

Non-Compliance & Execution
2
Stage 122/01/2026

Delay condonation

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to non-compliance with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.

3
Stage 215/12/2025

Delay condonation

The Tribunal directed the appellant to deposit the remaining amount required under Section 43(5) of the RERA Act, 2016, and instructed the Registry to report on the adequacy of the deposit.

4
Stage 320/11/2025

Delay condonation

The Tribunal granted the appellant a final opportunity to fully comply with the mandate of Section 43(5) of the Act, 2016, noting a shortfall in the required deposit relative to the Recovery Certificate.

5
Stage 404/11/2025

Delay condonation

The Tribunal granted the appellant time to file calculations regarding Section 43(5) compliance and to seek further instructions, adjourning the matter to 20.11.2025.

6
Stage 510/10/2025

Delay condonation

The Tribunal has directed the appellant's counsel to satisfy the mandate of Section 43 (5) of the Act 2016 and listed the appeal for hearing on 04.11.2025.

7
Stage 618/09/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections, with a subsequent one-week window for a rejoinder, and scheduled the appeal for hearing on 10.10.2025.

8
Stage 728/08/2025

Delay condonation

The Tribunal granted the appellant seven days to file a rejoinder affidavit regarding objections to a delay condonation application and scheduled the next hearing for 18.09.2025.

9
Stage 814/08/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with a subsequent week allowed for the appellant to reply.

10
Stage 9Interim Order

Tribunal Order #0901126040352024-15-12-2025

The Tribunal directed the appellant to deposit the remaining amount required under Section 43(5) of the RERA Act, 2016, and instructed the Registry to report on the adequacy of the deposit.

11
Stage 10Final Ruling Order

Tribunal Order #0901126040352024-22-01-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to non-compliance with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.

12
Stage 11Interim Order

Tribunal Order #0901126040352024-20-11-2025

The Tribunal granted the appellant a final opportunity to fully comply with the mandate of Section 43(5) of the Act, 2016, noting a shortfall in the required deposit relative to the Recovery Certificate.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to non-compliance with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to non-compliance with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Gautam Johri

Respondent Advocate(s)

  • Amit Yadav
  • V. P. Singh

Official RERA Tribunal Orders (3)

INTERIM_ORDEROrder ID: 0901126040352024-15-12-2025

The Tribunal directed the appellant to deposit the remaining amount required under Section 43(5) of the RERA Act, 2016, and instructed the Registry to report on the adequacy of the deposit.

FINAL_ORDEROrder ID: 0901126040352024-22-01-2026

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Awas Evam Vikas Parishad due to non-compliance with the mandatory deposit requirements under Section 43(5) of the Act, 2016, and directed the remittance of previously deposited funds to U.P. RERA for disbursement.

INTERIM_ORDEROrder ID: 0901126040352024-20-11-2025

The Tribunal granted the appellant a final opportunity to fully comply with the mandate of Section 43(5) of the Act, 2016, noting a shortfall in the required deposit relative to the Recovery Certificate.