up_reraStatus: Completed
CASE ID: 0901126039502021

Appellant / Complainant

Anurag Maheshwari

VS

Respondent

Jitendra Kumar Mangla, Prerna Construction Pvt Ltd

Developer Firm

prerna construction pvt ltd

Disputed Amount

20,08,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & ExecutionJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126039502021 by Anurag Maheshwari against Jitendra Kumar Mangla, Prerna Construction Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title TransferNon-Compliance & ExecutionJurisdiction & Maintainability
2
Stage 130/03/2022

Ex-Parte

The Tribunal set aside the Regulatory Authority's order that had erroneously rejected the appellant's complaint by misinterpreting an Agreement for Sale as a Conveyance Deed, and remanded the matter back to the Regulatory Authority for fresh adjudication.

3
Stage 222/03/2022

For Order

The Tribunal declares service of notice sufficient via publication and email and proceeds ex-parte against the respondent due to their failure to appear despite multiple opportunities.

4
Stage 324/02/2022

Notice

The Tribunal directed the appellant to serve the appeal documents via the respondent's registered email and warned that the matter may proceed ex-parte if no objections are filed by the next hearing on 22.03.2022.

5
Stage 413/01/2022

Notice

No text available.

6
Stage 508/12/2021

Further Order

The Tribunal ruled that the previous method of service was insufficient and directed the appellant to publish notice in a widely circulated newspaper in District Agra within 20 days.

7
Stage 616/11/2021

Notice

The Tribunal noted that the respondent had not been served notice and directed the appellant to issue notice via dasti, registered post, and e-mail within one week.

8
Stage 724/09/2021

Hearing on Appeal

The Tribunal issued notice to the respondents via registered post and email and scheduled the appeal for further orders on 16.11.2021.

9
Stage 8Final Ruling Order

Tribunal Order #0901126039502021-30-03-2022

The Tribunal set aside the Regulatory Authority's order that had erroneously rejected the appellant's complaint by misinterpreting an Agreement for Sale as a Conveyance Deed, and remanded the matter back to the Regulatory Authority for fresh adjudication.

10
Stage 9Interim Order

Tribunal Order #0901126039502021-22-03-2022

The Tribunal declares service of notice sufficient via publication and email and proceeds ex-parte against the respondent due to their failure to appear despite multiple opportunities.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order that had erroneously rejected the appellant's complaint by misinterpreting an Agreement for Sale as a Conveyance Deed, and remanded the matter back to the Regulatory Authority for fresh adjudication. Awarded in favor of Appellant. Awarded interest rate: 18% p.a..

Disposal Winner: AppellantInterest Rate: 18% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order that had erroneously rejected the appellant's complaint by misinterpreting an Agreement for Sale as a Conveyance Deed, and remanded the matter back to the Regulatory Authority for fresh adjudication.

Ruling Awarded To

Appellant

Awarded Interest Rate

18% p.a.

Interest Period

from the date of first deposit (19.07.2016) till the date of refund of entire amount deposited

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 40Section 63Section 64Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Fuhar Gupta

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126039502021-30-03-2022

The Tribunal set aside the Regulatory Authority's order that had erroneously rejected the appellant's complaint by misinterpreting an Agreement for Sale as a Conveyance Deed, and remanded the matter back to the Regulatory Authority for fresh adjudication.

INTERIM_ORDEROrder ID: 0901126039502021-22-03-2022

The Tribunal declares service of notice sufficient via publication and email and proceeds ex-parte against the respondent due to their failure to appear despite multiple opportunities.

TathyaGrid RERA Intelligence AI

Need to research all rulings for prerna construction pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →