Appellant / Complainant
Emaar Mgf Land Limited
Respondent
Real Estate Regulatory Authority, Vinay Kumar Agarwal, Anr.
emaar mgf land limited
Appellant
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126039202023 by Emaar Mgf Land Limited against Real Estate Regulatory Authority, Vinay Kumar Agarwal, Anr. before up_rera.
Admission
The U.P. Real Estate Appellate Tribunal allowed the appeal filed by Emaar MGF Land Limited, referring to a separate order passed in Appeal No. 621/2023 for the specific details of the ruling.
Admission
The Tribunal refers the parties to a previously passed order dated 20.03.2024 in Appeal No. 621/2023 for the directions contained therein.
Admission
The Tribunal denied the respondent's request for a two-week extension and instead granted only 10 days to file objections, imposing a cost of Rs. 1000/- on the respondent.
Admission
The Tribunal granted the respondent seven days to file objections to the grounds of appeal and directed the appellant to file a reply within three days of receiving said objections.
Defect Removal
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.
Tribunal Order #0901126039202023-19-04-2024
The U.P. Real Estate Appellate Tribunal allowed the appeal filed by Emaar MGF Land Limited, referring to a separate order passed in Appeal No. 621/2023 for the specific details of the ruling.
Tribunal Order #0901126039202023-20-02-2024
The Tribunal denied the respondent's request for a two-week extension and instead granted only 10 days to file objections, imposing a cost of Rs. 1000/- on the respondent.
Tribunal Order #0901126039202023-22-09-2023
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The U.P. Real Estate Appellate Tribunal allowed the appeal filed by Emaar MGF Land Limited, referring to a separate order passed in Appeal No. 621/2023 for the specific details of the ruling. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The U.P. Real Estate Appellate Tribunal allowed the appeal filed by Emaar MGF Land Limited, referring to a separate order passed in Appeal No. 621/2023 for the specific details of the ruling.
Ruling Awarded To
Appellant
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Singh
Respondent Advocate(s)
- Amit Yadav
- Vinay K Lakhani
Official RERA Tribunal Orders (3)
The U.P. Real Estate Appellate Tribunal allowed the appeal filed by Emaar MGF Land Limited, referring to a separate order passed in Appeal No. 621/2023 for the specific details of the ruling.
The Tribunal denied the respondent's request for a two-week extension and instead granted only 10 days to file objections, imposing a cost of Rs. 1000/- on the respondent.
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.