up_reraStatus: Completed
CASE ID: 0901126039062021

Appellant / Complainant

Nikhil Srivastava, Pooja Srivastava

VS

Respondent

Stellar Constellation Projects Private Limited

Developer Firm

stellar constellation projects private limited

Disputed Amount

53,27,375

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

28 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126039062021 by Nikhil Srivastava, Pooja Srivastava against Stellar Constellation Projects Private Limited before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 131/05/2023

for delivery of Judgment/Order

The Appellate Tribunal set aside the UPRERA order that had dismissed the appellant's complaint, ruling that the project was an 'ongoing project' requiring registration and remanding the matter back to the Regulatory Authority for a fresh decision on delay interest.

3
Stage 215/05/2023

Hearing

The Tribunal heard arguments regarding whether the respondent's project required registration under the Act 2016, specifically addressing whether applying for an OC/CC prior to the Act's promulgation exempts a project from registration. The judgment has been reserved.

4
Stage 325/04/2023

Hearing

The Tribunal granted the appellant one week to prepare arguments regarding whether the respondent's unregistered project qualifies as an 'ongoing project' and adjourned the matter to 15.05.2023.

5
Stage 415/03/2023

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for hearing/orders on 25.04.2023.

6
Stage 507/02/2023

Hearing

The Tribunal ruled that the respondent is liable to pay interest for delay in possession from 20.08.2015 to 28.02.2019 and noted that the project required registration due to partial OCs; the matter is adjourned for 15 days to allow parties to attempt an amicable settlement.

7
Stage 606/02/2023

Hearing

The Tribunal granted the appellant 24 hours to file an online complaint previously submitted to the Regulatory Authority and rescheduled the hearing for February 7, 2023.

8
Stage 721/12/2022

Further Order

The Tribunal notes that pleadings have been exchanged between the parties and schedules the next hearing for February 6, 2023.

9
Stage 828/11/2022

Further Order

No text available.

10
Stage 902/11/2022

Further Order

The Tribunal directed the appellant's counsel to resolve a technical issue regarding the visibility of their filed reply on the portal and scheduled the matter for hearing on 28.11.2022.

11
Stage 1028/09/2022

Further Order

The Tribunal noted the respondent's submission regarding the project status and directed the appellant to file any rebuttal papers before listing the appeal for hearing on 02.11.2022.

12
Stage 1130/08/2022

Further Order

The Tribunal directed the respondent to provide factual evidence demonstrating whether the project was ongoing at the commencement of the RERA Act, 2016, and scheduled the matter for further orders on 28.09.2022.

13
Stage 1205/08/2022

Further Order

The Tribunal noted the absence of the appellant and, upon submission by the respondent's counsel that pleadings are complete, scheduled the appeal for hearing on 30.08.2022.

14
Stage 1322/07/2022

Further Order

The Tribunal granted a request from the counsels of both parties to adjourn the appeal and rescheduled the hearing for 05.08.2022.

15
Stage 1411/05/2022

Further Order

The Tribunal granted the appellant's request for time to file a replication against the respondent's reply and scheduled the next hearing for 22.07.2022.

16
Stage 1507/04/2022

Delay condonation

The Tribunal condoned a 186-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the appellant to file a replication/rejoinder affidavit.

17
Stage 1614/03/2022

Delay condonation

The Tribunal granted an adjournment due to the respondent's counsel's illness and directed the respondent to serve objections to the grounds of appeal within 10 days.

18
Stage 1722/02/2022

Delay condonation

The Tribunal granted the applicant 10 days to file a reply to objections regarding the condonation of delay and directed the respondent to serve its objections via email within one week.

19
Stage 1812/01/2022

Delay condonation

No text available.

20
Stage 1916/12/2021

Delay condonation

The Tribunal directed the respondent to file their Vakalatnama and objections against the limitation application before the next hearing date. The matter is scheduled for further orders on 12.01.2022.

21
Stage 2023/11/2021

Notice

The Tribunal adjourned the matter to 16.12.2021 for the disposal of a limitation application and directed both parties to appear on the next date.

22
Stage 2130/09/2021

Delay condonation

The Tribunal noted that the appeal was filed beyond the limitation period and directed the issuance of notice to the respondent, scheduling the matter for further hearing on 23.11.2021.

23
Stage 22Final Ruling Order

Tribunal Order #0901126039062021-31-05-2023

The Appellate Tribunal set aside the UPRERA order that had dismissed the appellant's complaint, ruling that the project was an 'ongoing project' requiring registration and remanding the matter back to the Regulatory Authority for a fresh decision on delay interest.

24
Stage 23Interim Order

Tribunal Order #0901126039062021-15-05-2023

The Tribunal heard arguments regarding whether the respondent's project required registration under the Act 2016, specifically addressing whether applying for an OC/CC prior to the Act's promulgation exempts a project from registration. The judgment has been reserved.

25
Stage 24Interim Order

Tribunal Order #0901126039062021-07-02-2023

The Tribunal ruled that the respondent is liable to pay interest for delay in possession from 20.08.2015 to 28.02.2019 and noted that the project required registration due to partial OCs; the matter is adjourned for 15 days to allow parties to attempt an amicable settlement.

26
Stage 25Interim Order

Tribunal Order #0901126039062021-30-08-2022

The Tribunal directed the respondent to provide factual evidence demonstrating whether the project was ongoing at the commencement of the RERA Act, 2016, and scheduled the matter for further orders on 28.09.2022.

27
Stage 26Interim Order

Tribunal Order #0901126039062021-07-04-2022

The Tribunal condoned a 186-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the appellant to file a replication/rejoinder affidavit.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal set aside the UPRERA order that had dismissed the appellant's complaint, ruling that the project was an 'ongoing project' requiring registration and remanding the matter back to the Regulatory Authority for a fresh decision on delay interest. Awarded in favor of Appellant. Awarded interest rate: 12% p.a..

Disposal Winner: AppellantInterest Rate: 12% p.a.Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal set aside the UPRERA order that had dismissed the appellant's complaint, ruling that the project was an 'ongoing project' requiring registration and remanding the matter back to the Regulatory Authority for a fresh decision on delay interest.

Ruling Awarded To

Appellant

Awarded Interest Rate

12% p.a.

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Ram Kumar Verma

Respondent Advocate(s)

  • Arvind Kumar

Official RERA Tribunal Orders (5)

FINAL_ORDEROrder ID: 0901126039062021-31-05-2023

The Appellate Tribunal set aside the UPRERA order that had dismissed the appellant's complaint, ruling that the project was an 'ongoing project' requiring registration and remanding the matter back to the Regulatory Authority for a fresh decision on delay interest.

INTERIM_ORDEROrder ID: 0901126039062021-15-05-2023

The Tribunal heard arguments regarding whether the respondent's project required registration under the Act 2016, specifically addressing whether applying for an OC/CC prior to the Act's promulgation exempts a project from registration. The judgment has been reserved.

INTERIM_ORDEROrder ID: 0901126039062021-07-02-2023

The Tribunal ruled that the respondent is liable to pay interest for delay in possession from 20.08.2015 to 28.02.2019 and noted that the project required registration due to partial OCs; the matter is adjourned for 15 days to allow parties to attempt an amicable settlement.

INTERIM_ORDEROrder ID: 0901126039062021-30-08-2022

The Tribunal directed the respondent to provide factual evidence demonstrating whether the project was ongoing at the commencement of the RERA Act, 2016, and scheduled the matter for further orders on 28.09.2022.

INTERIM_ORDEROrder ID: 0901126039062021-07-04-2022

The Tribunal condoned a 186-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the appellant to file a replication/rejoinder affidavit.

TathyaGrid RERA Intelligence AI

Need to research all rulings for stellar constellation projects private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →