Appellant / Complainant
Emaar Mgf Land Limited
Respondent
Vinay Kumar Agarwal, Real Estate Regulatory Authority
emaar mgf land limited
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126038942023 by Emaar Mgf Land Limited against Vinay Kumar Agarwal, Real Estate Regulatory Authority before up_rera.
Admission
The Tribunal set aside the UPRERA impugned order dated June 9, 2023, due to violations of the principles of natural justice, and remanded the matter back to the Regulatory Authority for a fresh hearing after allowing both parties to file replies/objections to new documents.
Admission
The Tribunal noted a request for adjournment from the respondent's counsel due to him being out of station and rescheduled the appeal for hearing on 19.04.2024.
Admission
The Tribunal denied the respondent's request for a two-week extension to file objections, instead granting only 10 days subject to a cost of Rs. 1000/- imposed on the respondent.
Admission
The Tribunal granted the respondent seven days to file objections to the appeal and directed the appellant to file a reply within three days of receiving said objections.
Defect Removal
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.
Tribunal Order #0901126038942023-19-04-2024
The Tribunal set aside the UPRERA impugned order dated June 9, 2023, due to violations of the principles of natural justice, and remanded the matter back to the Regulatory Authority for a fresh hearing after allowing both parties to file replies/objections to new documents.
Tribunal Order #0901126038942023-20-02-2024
The Tribunal denied the respondent's request for a two-week extension to file objections, instead granting only 10 days subject to a cost of Rs. 1000/- imposed on the respondent.
Tribunal Order #0901126038942023-22-09-2023
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the UPRERA impugned order dated June 9, 2023, due to violations of the principles of natural justice, and remanded the matter back to the Regulatory Authority for a fresh hearing after allowing both parties to file replies/objections to new documents. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the UPRERA impugned order dated June 9, 2023, due to violations of the principles of natural justice, and remanded the matter back to the Regulatory Authority for a fresh hearing after allowing both parties to file replies/objections to new documents.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Singh
Respondent Advocate(s)
- Amit Yadav
- Vinay K Lakhani
Official RERA Tribunal Orders (3)
The Tribunal set aside the UPRERA impugned order dated June 9, 2023, due to violations of the principles of natural justice, and remanded the matter back to the Regulatory Authority for a fresh hearing after allowing both parties to file replies/objections to new documents.
The Tribunal denied the respondent's request for a two-week extension to file objections, instead granting only 10 days subject to a cost of Rs. 1000/- imposed on the respondent.
The Tribunal allowed the appellant's waiver application regarding Section 43(5) deposit requirements because the impugned order imposed no financial liability, and subsequently directed the conversion of the defective appeal into a regular appeal.
Need to research all rulings for emaar mgf land limited?