up_reraStatus: Completed
CASE ID: 0901126038852023

Appellant / Complainant

Anil Kumar Singh

VS

Respondent

Kanpur Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

16 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126038852023 by Anil Kumar Singh against Kanpur Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 107/02/2025

Re-Hearing

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to delay interest from 16.06.2019 to 11.11.2020 (minus a six-month COVID-19 force majeure period), affirming that statutory rights to interest cannot be waived by the execution of a sale deed.

3
Stage 210/01/2025

For Order

Upon the joint request of both parties, the appeal has been adjourned for orders or hearing on 07.02.2025.

4
Stage 325/07/2024

Hearing

The Tribunal heard arguments from both parties regarding the appeal and has reserved its judgment for a later date.

5
Stage 427/05/2024

Hearing

The Tribunal granted an adjournment request from the respondent's counsel on personal grounds but warned that no further adjournments will be permitted at the next hearing.

6
Stage 521/05/2024

Hearing

The Tribunal adjourned the proceedings to 27.05.2024 due to the absence of the respondent and issued a strict directive that no further adjournments will be granted on the next date.

7
Stage 614/05/2024

Hearing

The Tribunal granted a request from the respondent's counsel for additional time to address a query regarding reliance on overruled judgments and adjourned the matter to 21.05.2024.

8
Stage 713/05/2024

Hearing

The Tribunal granted an adjournment to allow the appellant's counsel time to address objections regarding the maintainability of a second complaint filed for the same cause of action, rescheduling the matter for 14.05.2024.

9
Stage 810/04/2024

Admission

No text available.

10
Stage 906/03/2024

Admission

The respondent's counsel requested an adjournment of the proceedings, and the tribunal rescheduled the hearing to 10.04.2024.

11
Stage 1029/01/2024

Admission

The Tribunal granted the appellant a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for March 6, 2024.

12
Stage 1130/10/2023

Admission

No text available.

13
Stage 1218/09/2023

Admission

The Tribunal issued a notice to the respondent and outlined specific procedural instructions for service of notice via speed-post and email, scheduling the next hearing for 30.10.2023.

14
Stage 1314/09/2023

Admission

The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the matter for 18.09.2023.

15
Stage 14Final Ruling Order

Tribunal Order #0901126038852023-07-02-2025

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to delay interest from 16.06.2019 to 11.11.2020 (minus a six-month COVID-19 force majeure period), affirming that statutory rights to interest cannot be waived by the execution of a sale deed.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to delay interest from 16.06.2019 to 11.11.2020 (minus a six-month COVID-19 force majeure period), affirming that statutory rights to interest cannot be waived by the execution of a sale deed. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to delay interest from 16.06.2019 to 11.11.2020 (minus a six-month COVID-19 force majeure period), affirming that statutory rights to interest cannot be waived by the execution of a sale deed.

Ruling Awarded To

Appellant

Interest Period

from 16.06.2019 until 11.11.2020 deducting six months towards covid pandemic force majeure

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Jayant Gupta
  • Anjali Singh
  • Shikhar Nigam

Respondent Advocate(s)

  • Bhupendra Singh
  • Somendra Pal Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126038852023-07-02-2025

The Tribunal set aside the Regulatory Authority's order, ruling that the appellant is entitled to delay interest from 16.06.2019 to 11.11.2020 (minus a six-month COVID-19 force majeure period), affirming that statutory rights to interest cannot be waived by the execution of a sale deed.