up_reraStatus: Completed
CASE ID: 0901126038432024

Appellant / Complainant

Gorakhpur Development Authority

VS

Respondent

Ram Nagina Yadav

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

8 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126038432024 by Gorakhpur Development Authority against Ram Nagina Yadav before up_rera.

Delay Compensation / Interest
2
Stage 124/02/2025

Hearing on Recall App

The Tribunal condoned the delay in filing the recall application and disposed of the appeal by applying the precedent set in Kamla Chaurasiya, specifically modifying the impugned order to exclude the period from 17.12.2018 to 12.01.2021 from delay interest calculations due to an NGT injunction.

3
Stage 229/01/2025

Hearing on Recall App

The Tribunal has rescheduled the matter to 24.02.2025 for the disposal of both the recall application and the appeal, noting that no further adjournments will be granted.

4
Stage 306/01/2025

Hearing on Recall App

Both parties sought an adjournment, resulting in the matter being rescheduled for hearing on 29.01.2025.

5
Stage 420/11/2024

Hearing on Recall App

The Tribunal adjourned the matter to 06.01.2025 and directed the parties to complete the exchange of pleadings regarding objections to the application for condonation of delay.

6
Stage 517/10/2024

Hearing on Recall App

The Tribunal issued notice to the respondent regarding an application for condonation of delay and recall of an order dated 03.05.2024, scheduling the matter for hearing on 20.11.2024.

7
Stage 6Final Ruling Order

Tribunal Order #0901126038432024-24-02-2025

The Tribunal condoned the delay in filing the recall application and disposed of the appeal by applying the precedent set in Kamla Chaurasiya, specifically modifying the impugned order to exclude the period from 17.12.2018 to 12.01.2021 from delay interest calculations due to an NGT injunction.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal condoned the delay in filing the recall application and disposed of the appeal by applying the precedent set in Kamla Chaurasiya, specifically modifying the impugned order to exclude the period from 17.12.2018 to 12.01.2021 from delay interest calculations due to an NGT injunction. Awarded in favor of Partial.

Disposal Winner: PartialStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal condoned the delay in filing the recall application and disposed of the appeal by applying the precedent set in Kamla Chaurasiya, specifically modifying the impugned order to exclude the period from 17.12.2018 to 12.01.2021 from delay interest calculations due to an NGT injunction.

Ruling Awarded To

Partial

Interest Period

The period w.e.f. 17.12.2018 to 12.01.2021 shall be excluded from the period while computing delay interest

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126038432024-24-02-2025

The Tribunal condoned the delay in filing the recall application and disposed of the appeal by applying the precedent set in Kamla Chaurasiya, specifically modifying the impugned order to exclude the period from 17.12.2018 to 12.01.2021 from delay interest calculations due to an NGT injunction.