up_reraStatus: Completed
CASE ID: 0901126038162024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Devendrajeet Maurya

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

14 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126038162024 by Lucknow Development Authority against Devendrajeet Maurya before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 129/10/2025

Part Heard

The U.P. Real Estate Appellate Tribunal condoned a 414-day delay in filing the appeal and set aside the Adjudicating Officer's order, ruling that while the previous order was without jurisdiction, the respondent is entitled to delay interest at MCLR+1% per annum for the period of project delay.

3
Stage 222/09/2025

Part Heard

No text available.

4
Stage 318/09/2025

Delay condonation

The Tribunal heard arguments from the counsel for both parties and adjourned the appeal for further arguments on 22.09.2025.

5
Stage 402/09/2025

Delay condonation

The Tribunal scheduled the appeal for a final hearing on 18.09.2025 and issued a strict directive that no further adjournments will be granted to the respondent.

6
Stage 512/08/2025

Delay condonation

The Tribunal granted the appellant a one-week extension to file a rejoinder to the respondent's objections and scheduled the matter for hearing on 02.09.2025 regarding the application for condonation of delay.

7
Stage 605/08/2025

Delay condonation

Upon a joint request from the counsel for both parties, the Tribunal has adjourned the appeal and scheduled it to be listed on 12.08.2025.

8
Stage 716/07/2025

Delay condonation

The Tribunal granted the appellant a 10-day extension to file a rejoinder and scheduled the next hearing for August 5, 2025.

9
Stage 827/05/2025

Hearing

The Tribunal granted the appellant a one-week extension to file a rejoinder affidavit and scheduled the case for orders on 16.07.2025.

10
Stage 915/05/2025

Delay condonation

The Tribunal granted the appellant's counsel time to file a rejoinder and adjourned the appeal to 27.05.2025.

11
Stage 1021/04/2025

Delay condonation

The Tribunal granted the respondent 10 days to file objections and directed the appellant to reply within one week thereafter, scheduling the next hearing for May 15, 2025.

12
Stage 1124/03/2025

Delay condonation

The Tribunal issued notice to the respondent and directed the applicant to serve the appeal documents via post and email, scheduling the next hearing for April 21, 2025.

13
Stage 12Final Ruling Order

Tribunal Order #0901126038162024-29-10-2025

The U.P. Real Estate Appellate Tribunal condoned a 414-day delay in filing the appeal and set aside the Adjudicating Officer's order, ruling that while the previous order was without jurisdiction, the respondent is entitled to delay interest at MCLR+1% per annum for the period of project delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal condoned a 414-day delay in filing the appeal and set aside the Adjudicating Officer's order, ruling that while the previous order was without jurisdiction, the respondent is entitled to delay interest at MCLR+1% per annum for the period of project delay. Awarded in favor of Partial. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: PartialInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal condoned a 414-day delay in filing the appeal and set aside the Adjudicating Officer's order, ruling that while the previous order was without jurisdiction, the respondent is entitled to delay interest at MCLR+1% per annum for the period of project delay.

Ruling Awarded To

Partial

Awarded Interest Rate

MCLR+1% per annum

Interest Period

w.e.f. 31.08.2015 to 26.07.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Suyash Gupta

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126038162024-29-10-2025

The U.P. Real Estate Appellate Tribunal condoned a 414-day delay in filing the appeal and set aside the Adjudicating Officer's order, ruling that while the previous order was without jurisdiction, the respondent is entitled to delay interest at MCLR+1% per annum for the period of project delay.