Appellant / Complainant
Lucknow Development Authority
Respondent
Himanshu Sharma
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126038152024 by Lucknow Development Authority against Himanshu Sharma before up_rera.
Hearing
The Tribunal condoned a 424-day delay in filing the appeal and subsequently set aside the Adjudicating Officer's order, ruling that while the respondent is entitled to delay interest (MCLR+1% per annum) for the admitted period of 31.08.2015 to 09.08.2019, the original order was quashed.
Part Heard
The Tribunal noted that the appeal had previously proceeded ex-parte against the respondent and scheduled the matter for a further hearing on 05.12.2025.
Part Heard
The Tribunal granted a request by the appellant's counsel to reschedule the hearing of Appeal-90/2025 to 18.11.2025.
Delay condonation
The Tribunal has adjourned the appeal to 22.09.2025 in the interest of justice due to the absence of the respondent.
Delay condonation
The Tribunal noted the filing of a rejoinder by the appellant and scheduled the appeal for final hearing on 18.09.2025, while explicitly prohibiting further adjournments for the respondent.
Delay condonation
The Tribunal has scheduled a hearing for 02.09.2025 to consider an application for condonation of delay regarding the appellant's defective appeal.
Delay condonation
The Tribunal granted a request from the counsel for both parties to adjourn the appeal and rescheduled the matter for hearing on 12.08.2025.
Delay condonation
The Tribunal granted the appellant a final 10-day extension to file a rejoinder and scheduled the next hearing for August 5, 2025.
Hearing
The Tribunal granted the appellant one week's time to file a rejoinder affidavit and scheduled the case for orders on 16.07.2025.
Delay condonation
The Tribunal noted that the respondent was duly served but failed to appear, and consequently ordered the appeal to be heard ex-parte on 27.05.2025.
Delay condonation
The Tribunal noted the service of notice upon the respondent and granted them 10 days to file objections, with the matter scheduled for hearing on 15.05.2025.
Delay condonation
The Tribunal issued a notice to the respondent and outlined the procedural timeline for service of documents, filing objections to the condonation of delay, and subsequent replies.
Tribunal Order #0901126038152024-05-12-2025
The Tribunal condoned a 424-day delay in filing the appeal and subsequently set aside the Adjudicating Officer's order, ruling that while the respondent is entitled to delay interest (MCLR+1% per annum) for the admitted period of 31.08.2015 to 09.08.2019, the original order was quashed.
Tribunal Disposal & Final Award Ruling
The Tribunal condoned a 424-day delay in filing the appeal and subsequently set aside the Adjudicating Officer's order, ruling that while the respondent is entitled to delay interest (MCLR+1% per annum) for the admitted period of 31.08.2015 to 09.08.2019, the original order was quashed. Awarded in favor of Partial. Awarded interest rate: MCLR+1% per annum.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal condoned a 424-day delay in filing the appeal and subsequently set aside the Adjudicating Officer's order, ruling that while the respondent is entitled to delay interest (MCLR+1% per annum) for the admitted period of 31.08.2015 to 09.08.2019, the original order was quashed.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR+1% per annum
Interest Period
w.e.f. 31.08.2015 to 09.08.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (1)
The Tribunal condoned a 424-day delay in filing the appeal and subsequently set aside the Adjudicating Officer's order, ruling that while the respondent is entitled to delay interest (MCLR+1% per annum) for the admitted period of 31.08.2015 to 09.08.2019, the original order was quashed.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.