up_reraStatus: Completed
CASE ID: 0901126038092024

Appellant / Complainant

Diograzia Realcon Pvt. Ltd. Through Its Representative Manish Tiwari

VS

Respondent

Bhutani Group

Developer Firm

bhutani group

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

22 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126038092024 by Diograzia Realcon Pvt. Ltd. Through Its Representative Manish Tiwari against Bhutani Group before up_rera.

Delay in PossessionDelay Compensation / InterestSale Deed & Title TransferJurisdiction & Maintainability
2
Stage 119/05/2026

for delivery of Judgment/Order

The Tribunal dismissed all eleven appeals and quashed the impugned order, ruling that claims regarding the possession of virtual/unlockable office space and the payment of assured returns are not maintainable under the provisions of the RERA Act, 2016.

3
Stage 215/05/2026

for delivery of Judgment/Order

No text available.

4
Stage 320/01/2026

Final Hearing

The Tribunal heard arguments from both parties regarding the appeal and objections, but has reserved the judgment for a later date.

5
Stage 410/12/2025

Hearing

The Tribunal has granted a request to list Appeal-383/2024 for final hearing on 20.01.2026, along with several related appeal records.

6
Stage 513/11/2025

Hearing

Upon the joint request of the counsels for both parties, the Tribunal has adjourned the appeal to be listed for hearing on 10.12.2025.

7
Stage 616/10/2025

Hearing

The Tribunal granted the respondent counsel additional time to prepare his brief and scheduled the appeal for a hearing on November 13, 2025.

8
Stage 717/09/2025

Hearing

The Tribunal granted the appellant ten days to file a rejoinder affidavit following an adjournment application by the respondent and scheduled the next hearing for 16.10.2025.

9
Stage 801/09/2025

Hearing

The Tribunal granted the respondent seven days to upload additional annexures to their objections and allowed the appellant seven days thereafter to file a rejoinder affidavit, with the matter listed for 17.09.2025.

10
Stage 904/08/2025

Hearing

The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the next hearing for September 1, 2025.

11
Stage 1009/07/2025

Hearing

The Tribunal granted the respondent 10 days to file objections, with the appellant permitted to file a reply within one week thereafter, and scheduled the next hearing for August 4, 2025.

12
Stage 1115/05/2025

Hearing

The Tribunal granted the respondent ten days to file their Vakalatnama and objections, after which the appellant may file a reply; the matter is scheduled for hearing on 09.07.2025.

13
Stage 1225/04/2025

Hearing

The Tribunal granted the respondent ten days to file objections and allowed the appellant seven days to file a rejoinder, scheduling the case for orders on 15.05.2025.

14
Stage 1302/04/2025

Hearing

The Tribunal refers the parties to a previous order passed in Appeal No. 382/2024 for the directions regarding this matter.

15
Stage 1407/03/2025

Hearing

The Tribunal refers the parties to a previous order passed in Appeal No. 382/2024 for the directions regarding this matter.

16
Stage 1512/02/2025

Hearing

The Tribunal granted the respondent ten days to file objections to the memo of appeal and directed the appellant to file a rejoinder within one week of receiving said objections.

17
Stage 1622/01/2025

Hearing

The Tribunal adjourned the matter to 12.02.2025 for orders due to the absence of the respondent.

18
Stage 1716/12/2024

Hearing

The Tribunal adjourned the appeal to 22.01.2025 and directed the respondent to file objections within 10 days, with a subsequent one-week window for the appellant to file a reply.

19
Stage 1828/11/2024

Admission

No text available.

20
Stage 1923/10/2024

Admission

The Tribunal issued notice to the respondent and established a procedural timeline for service of appeal documents and exchange of objections prior to the next hearing on 28.11.2024.

21
Stage 20Final Ruling Order

Tribunal Order #0901126038092024-19-05-2026

The Tribunal dismissed all eleven appeals and quashed the impugned order, ruling that claims regarding the possession of virtual/unlockable office space and the payment of assured returns are not maintainable under the provisions of the RERA Act, 2016.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal dismissed all eleven appeals and quashed the impugned order, ruling that claims regarding the possession of virtual/unlockable office space and the payment of assured returns are not maintainable under the provisions of the RERA Act, 2016. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal dismissed all eleven appeals and quashed the impugned order, ruling that claims regarding the possession of virtual/unlockable office space and the payment of assured returns are not maintainable under the provisions of the RERA Act, 2016.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Pushpila Bisht
  • Himanshu Bora

Respondent Advocate(s)

  • Abhishek Shukla

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126038092024-19-05-2026

The Tribunal dismissed all eleven appeals and quashed the impugned order, ruling that claims regarding the possession of virtual/unlockable office space and the payment of assured returns are not maintainable under the provisions of the RERA Act, 2016.