Appellant / Complainant
Lucknow Development Authority
Respondent
Manoj Kumar Gupta
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126037062021 by Lucknow Development Authority against Manoj Kumar Gupta before up_rera.
for delivery of Judgment/Order
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.
Hearing
The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.
Hearing
The appeal was adjourned to 22.12.2022 following a request from the respondent's counsel due to the appellant's absence.
Hearing
Upon a joint request from the counsels for both parties, the appeal has been adjourned and listed for hearing on 20.12.2022.
Hearing
The Tribunal granted a request from the counsels of both parties to adjourn the appeal and rescheduled the matter for further orders on 15.12.2022.
Hearing
The Tribunal noted the absence of the appellant's counsel and adjourned the matter to 15.11.2022 for further orders.
Hearing
The Tribunal adjourned the appeal due to the absence of the appellant and scheduled it for hearing on 17.10.2022 along with cross Appeal No. (D) 351/2022.
Hearing
The Tribunal noted the absence of parties and ordered that Appeal-773/2021 be listed on 10.10.2022 along with cross Appeal No. (D) 351/2022.
Hearing
The Tribunal has ordered that this appeal be listed for hearing on 06.09.2022 to coincide with the scheduled cross-appeal.
Hearing
The Tribunal directed the Registry to list Appeal-773/2021 alongside cross Appeal No. D 351/2022 on 31.08.2022 for a joint hearing.
Delay condonation
The Tribunal condoned a 45-day delay in filing the appeal based on Supreme Court guidelines and directed the registry to convert the defective appeal into a regular appeal. The matter is scheduled to be heard alongside Appeal No. D-351/2022 on 05.08.2022.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the case for hearing on July 27, 2022, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted an adjournment request from the appellant's counsel due to personal difficulty and directed the parties to exchange pleadings before the next hearing on 13.07.2022.
Delay condonation
The Tribunal adjourned the matter to 23.05.2022 and directed both parties to exchange pleadings in the interim.
Delay condonation
The Tribunal granted the appellant a 10-day extension to file a reply to the respondent's objections and scheduled the matter for May 9, 2022, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the matter for April 18, 2022, to consider the application for condonation of delay.
Delay condonation
The Tribunal granted a final 10-day extension to the respondent for filing objections to the application for condonation of delay and grounds of appeal, warning that failure to comply will result in ex parte proceedings.
Defect Removal
The Tribunal granted a final 10-day extension to the respondent to file objections to the condonation of delay application and grounds of appeal, warning that failure to do so will result in an ex parte decision.
Defect Removal
The Tribunal adjourned the matter to 12.01.2022 and noted the Respondent's intention to file objections against the limitation application within 10 days.
Defect Removal
The Tribunal issued notice to the respondent via registered post and email and scheduled the matter for December 21, 2021, to address the limitation application and objections.
Tribunal Order #0901126037062021-30-12-2022
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.
Tribunal Order #0901126037062021-22-02-2022
The Tribunal granted a final 10-day extension to the respondent to file objections to the condonation of delay application and grounds of appeal, warning that failure to do so will result in an ex parte decision.
Tribunal Order #0901126037062021-27-07-2022
The Tribunal condoned a 45-day delay in filing the appeal based on Supreme Court guidelines and directed the registry to convert the defective appeal into a regular appeal. The matter is scheduled to be heard alongside Appeal No. D-351/2022 on 05.08.2022.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.
Ruling Awarded To
Respondent
Interest Period
from 27.04.2013 to 26.10.2016
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Surendra Kumar Sharma
Respondent Advocate(s)
- Atul Tripathi
Official RERA Tribunal Orders (3)
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the excluded period from 27.04.2013 to 26.10.2016 upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.
The Tribunal granted a final 10-day extension to the respondent to file objections to the condonation of delay application and grounds of appeal, warning that failure to do so will result in an ex parte decision.
The Tribunal condoned a 45-day delay in filing the appeal based on Supreme Court guidelines and directed the registry to convert the defective appeal into a regular appeal. The matter is scheduled to be heard alongside Appeal No. D-351/2022 on 05.08.2022.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.