Appellant / Complainant
Subhash Chandra
Respondent
Ansal Hi-Tech Townships Ltd.
ansal hi-tech townships ltd.
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126036422021 by Subhash Chandra against Ansal Hi-Tech Townships Ltd. before up_rera.
Hearing
The Tribunal modified the Regulatory Authority's order to correct a mistake, directing the respondent to provide an alternative plot of similar size instead of a unit in a tower, as the original agreement was for a plot.
Hearing
The matter was adjourned due to lack of time and is scheduled to be listed again on 24.05.2023.
Hearing
The Tribunal granted a request from the respondent's counsel to reschedule the hearing, listing the appeal for orders on 15.05.2023.
Hearing
The Tribunal noted that pleadings have been exchanged between the parties and adjourned the matter to 06.12.2022 for hearing.
Hearing
The Tribunal noted the filing of a replication/rejoinder by the appellant and adjourned the appeal to 11.11.2022 for hearing.
Hearing
The Tribunal granted the appellant a final opportunity to file a replication/rejoinder against the respondent's reply and scheduled the next hearing for 11.10.2022.
Hearing
The Tribunal directed the appellant to file a replication/rejoinder to the respondent's reply and scheduled the next hearing for September 7, 2022.
Hearing
The Tribunal directed the appellant to file a replication/rejoinder against the respondent's reply within 20 days and scheduled the next hearing for August 5, 2022.
Hearing
The Tribunal granted the respondent an extension of 20 days to file a reply against the grounds of appeal and scheduled the next hearing for May 31, 2022.
Hearing
The Tribunal directed the respondent to file a reply to the grounds of appeal and serve it to the appellant's counsel via email before the next hearing on 25.04.2022.
Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the appeal for hearing on 02.02.2022.
Hearing
The Tribunal directed the parties to upload their pleadings on the e-portal and file originals with the Registry before the next hearing date, which is scheduled for 10.01.2022.
Further Order
The Tribunal directed the respondent to file its Vakalatnama along with a reply to the grounds of appeal and provide copies to the appellant before the next hearing on 17.12.2021.
Notice
The Tribunal directed the respondent to file their Vakalat Nama and a reply to the grounds of appeal before the next hearing date.
Hearing on Appeal
The Tribunal noted that the appeal is within time and directed the issuance of notice to the respondent via registered post and email, scheduling the matter for further orders on 25.10.2021.
Tribunal Order #0901126036422021-04-08-2023
The Tribunal modified the Regulatory Authority's order to correct a mistake, directing the respondent to provide an alternative plot of similar size instead of a unit in a tower, as the original agreement was for a plot.
Tribunal Disposal & Final Award Ruling
The Tribunal modified the Regulatory Authority's order to correct a mistake, directing the respondent to provide an alternative plot of similar size instead of a unit in a tower, as the original agreement was for a plot. Awarded in favor of Appellant. Awarded interest rate: MCLR+1% p.a..
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal modified the Regulatory Authority's order to correct a mistake, directing the respondent to provide an alternative plot of similar size instead of a unit in a tower, as the original agreement was for a plot.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1% p.a.
Interest Period
from the promised period till receipt of OC/CC or offer of possession, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Prashant Kumar
- Fuhar Gupta
Respondent Advocate(s)
- Saurabh Misra
Official RERA Tribunal Orders (1)
The Tribunal modified the Regulatory Authority's order to correct a mistake, directing the respondent to provide an alternative plot of similar size instead of a unit in a tower, as the original agreement was for a plot.