Appellant / Complainant
Agarwal Associates (Promoters) Limited
Respondent
Shiv Bhanu Sharma, Anupama Sharma
agarwal associates (promoters) limited
₹10,81,184
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126036142025 by Agarwal Associates (Promoters) Limited against Shiv Bhanu Sharma, Anupama Sharma before up_rera.
Admission
The Tribunal set aside and quashed the order of the Real Estate Regulatory Authority, ruling that the complaint was not maintainable because the project had received its completion certificate prior to the commencement of the Act, 2016.
Admission
The Tribunal proceeded ex parte against the respondents due to their non-appearance and extended the interim order until the next hearing date of 19.03.2026.
Admission
The Tribunal granted the respondent a final ten-day extension to file objections, warning that the case will proceed ex parte if they fail to do so, and extended the interim order until the next hearing on 16.02.2026.
Admission
The Tribunal noted the successful service of notice upon the respondents and granted them ten days to file objections, followed by one week for a rejoinder, with the matter listed for orders on 05.01.2026.
Admission
The Tribunal granted the respondents an additional 10 days to file objections and scheduled the next hearing for November 26, 2025, while maintaining any existing interim orders.
Admission
The Tribunal granted a stay on the execution of the impugned judgment and decree dated 05.08.2025, pending the next hearing, following the appellant's compliance with the mandatory deposit under Section 43(5) of the Act.
Tribunal Order #0901126036142025-19-03-2026
The Tribunal set aside and quashed the order of the Real Estate Regulatory Authority, ruling that the complaint was not maintainable because the project had received its completion certificate prior to the commencement of the Act, 2016.
Tribunal Order #0901126036142025-14-10-2025
The Tribunal granted a stay on the execution of the impugned judgment and decree dated 05.08.2025, pending the next hearing, following the appellant's compliance with the mandatory deposit under Section 43(5) of the Act.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside and quashed the order of the Real Estate Regulatory Authority, ruling that the complaint was not maintainable because the project had received its completion certificate prior to the commencement of the Act, 2016. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside and quashed the order of the Real Estate Regulatory Authority, ruling that the complaint was not maintainable because the project had received its completion certificate prior to the commencement of the Act, 2016.
Ruling Awarded To
Appellant
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Saurabh Misra
- Gautam Johri
Official RERA Tribunal Orders (2)
The Tribunal set aside and quashed the order of the Real Estate Regulatory Authority, ruling that the complaint was not maintainable because the project had received its completion certificate prior to the commencement of the Act, 2016.
The Tribunal granted a stay on the execution of the impugned judgment and decree dated 05.08.2025, pending the next hearing, following the appellant's compliance with the mandatory deposit under Section 43(5) of the Act.
Need to research all rulings for agarwal associates (promoters) limited?