up_reraStatus: Completed
CASE ID: 0901126036012023

Appellant / Complainant

Manju Gupta

VS

Respondent

La-Residentia Developers Pvt Ltd

Developer Firm

la-residentia developers pvt ltd

Disputed Amount

35,62,426

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126036012023 by Manju Gupta against La-Residentia Developers Pvt Ltd before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / Interest
2
Stage 114/11/2024

Hearing

The Tribunal modified the Regulatory Authority's order to mandate that the respondent/promoter must forthwith refund the appellant's deposit with interest (MCLR+1%) within 45 days, ruling that an allottee's right to withdraw from a delayed project under Section 18 of the RERA Act is absolute and cannot be conditioned on a future completion date.

3
Stage 216/10/2024

Hearing

The court adjourned today's proceedings following an adjournment application by the respondent's counsel and scheduled the next hearing for November 14, 2024, noting that no further adjournments will be granted.

4
Stage 305/09/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for a final hearing on 16.10.2024.

5
Stage 406/08/2024

Hearing

The Tribunal recorded that pleadings have been exchanged and, upon joint request from both counsels, adjourned the matter to 05.09.2024 for hearing.

6
Stage 509/07/2024

Admission

The Tribunal granted the appellant additional time to study two Supreme Court judgments uploaded by the respondent and rescheduled the hearing for August 6, 2024.

7
Stage 610/05/2024

Admission

The Tribunal granted an adjournment requested by the appellant's counsel due to him being out of station and rescheduled the hearing for July 9, 2024.

8
Stage 709/04/2024

Admission

The Tribunal granted the appellant's counsel a one-week extension to file a reply to the respondent's objections and scheduled the next hearing for May 10, 2024.

9
Stage 806/03/2024

Admission

The Tribunal granted the appellant one week to file a reply to the objections raised by the respondent and scheduled the next hearing for 09.04.2024.

10
Stage 929/01/2024

Admission

The Tribunal granted the respondent a final 10-day extension to file objections to the appeal and directed that a soft copy be sent to the appellant's counsel.

11
Stage 1030/10/2023

Admission

No text available.

12
Stage 1118/09/2023

Admission

The Tribunal granted the respondent two weeks to file objections to the appeal and directed both parties to exchange copies via email and upload their respective filings to the e-portal before the next hearing on 30.10.2023.

13
Stage 1211/09/2023

Admission

The Tribunal adjourned the proceedings to 18.09.2023 due to a strike called by the Bar Council of Uttar Pradesh and the absence of legal counsel.

14
Stage 13Final Ruling Order

Tribunal Order #0901126036012023-14-11-2024

The Tribunal modified the Regulatory Authority's order to mandate that the respondent/promoter must forthwith refund the appellant's deposit with interest (MCLR+1%) within 45 days, ruling that an allottee's right to withdraw from a delayed project under Section 18 of the RERA Act is absolute and cannot be conditioned on a future completion date.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal modified the Regulatory Authority's order to mandate that the respondent/promoter must forthwith refund the appellant's deposit with interest (MCLR+1%) within 45 days, ruling that an allottee's right to withdraw from a delayed project under Section 18 of the RERA Act is absolute and cannot be conditioned on a future completion date. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal modified the Regulatory Authority's order to mandate that the respondent/promoter must forthwith refund the appellant's deposit with interest (MCLR+1%) within 45 days, ruling that an allottee's right to withdraw from a delayed project under Section 18 of the RERA Act is absolute and cannot be conditioned on a future completion date.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Shukla
  • Anuruddha Singh
  • Anand Verma

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126036012023-14-11-2024

The Tribunal modified the Regulatory Authority's order to mandate that the respondent/promoter must forthwith refund the appellant's deposit with interest (MCLR+1%) within 45 days, ruling that an allottee's right to withdraw from a delayed project under Section 18 of the RERA Act is absolute and cannot be conditioned on a future completion date.

TathyaGrid RERA Intelligence AI

Need to research all rulings for la-residentia developers pvt ltd?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →