CASE ID: 0901126035792021

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Atul Kumar

Disputed Amount

20,88,000

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126035792021 by U.P. Awas Evam Vikas Parishad against Atul Kumar before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 128/09/2022

for delivery of Judgment/Order

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order to pay interest as compensation for delayed possession of a flat, and directed the transfer of the promoter's pre-deposited amount to the U.P. RERA for disbursement to the allottee.

3
Stage 212/07/2022

Hearing

The Tribunal heard arguments regarding the maintainability of a claim following the execution of a conveyance deed and reserved its judgment for a later date.

4
Stage 324/05/2022

Delay condonation

The Tribunal granted an adjournment requested by the respondent due to personal difficulty and scheduled the appeal for a final hearing on 12.07.2022.

5
Stage 406/05/2022

Delay condonation

Due to the absence of the appellant's counsel, the Tribunal scheduled the appeal for a hearing on 24.05.2022.

6
Stage 530/03/2022

Delay condonation

The Tribunal condoned a 143-day delay in filing the appeal, citing COVID-19 pandemic relaxations granted by the Supreme Court, and directed the registry to register the defective appeal as a regular appeal.

7
Stage 610/03/2022

Delay condonation

The Tribunal granted the appellant 10 days to file a reply to the respondent's objections and scheduled the case for hearing on March 30, 2022.

8
Stage 705/01/2022

Further Order

The Tribunal directed the appellant to file an affidavit of service regarding the notice served on the respondent and scheduled the case for a further hearing on 28.01.2022.

9
Stage 810/12/2021

Further Order

The Tribunal granted an adjournment requested by the respondent's counsel and directed the respondent to file an objection against the appellant's limitation application within 10 days.

10
Stage 910/11/2021

Delay condonation

No text available.

11
Stage 1018/10/2021

Delay condonation

The Tribunal granted the appellant one week to file an affidavit of service and scheduled the defective appeal for a hearing on 10.11.2021.

12
Stage 1113/09/2021

Delay condonation

The Tribunal issued a notice to the respondent regarding the application for condonation of delay and directed the parties to exchange pleadings via email and post before the next hearing on 18.10.2021.

13
Stage 12Final Ruling Order

Tribunal Order #0901126035792021-28-09-2022

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order to pay interest as compensation for delayed possession of a flat, and directed the transfer of the promoter's pre-deposited amount to the U.P. RERA for disbursement to the allottee.

14
Stage 13Interim Order

Tribunal Order #0901126035792021-30-03-2022

The Tribunal condoned a 143-day delay in filing the appeal, citing COVID-19 pandemic relaxations granted by the Supreme Court, and directed the registry to register the defective appeal as a regular appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order to pay interest as compensation for delayed possession of a flat, and directed the transfer of the promoter's pre-deposited amount to the U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order to pay interest as compensation for delayed possession of a flat, and directed the transfer of the promoter's pre-deposited amount to the U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Interest Period

from 30.08.2015 to 01.11.2017

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Akhand Pratap Singh
  • Vijay Pratap Singh Chauhan

Respondent Advocate(s)

  • Jay Krishna Shukla

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126035792021-28-09-2022

The Uttar Pradesh Real Estate Appellate Tribunal dismissed the appeal filed by U.P. Avas Evam Vikas Parishad, upholding the Adjudicating Officer's order to pay interest as compensation for delayed possession of a flat, and directed the transfer of the promoter's pre-deposited amount to the U.P. RERA for disbursement to the allottee.

INTERIM_ORDEROrder ID: 0901126035792021-30-03-2022

The Tribunal condoned a 143-day delay in filing the appeal, citing COVID-19 pandemic relaxations granted by the Supreme Court, and directed the registry to register the defective appeal as a regular appeal.