Appellant / Complainant
Gorakhpur Development Authority
Respondent
Ram Sagar Dubey
₹3,02,756
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126035222024 by Gorakhpur Development Authority against Ram Sagar Dubey before up_rera.
For Order
The Tribunal allowed the application to correct a previous order, directing that the remaining amount of Rs. 3,02,756/- be remitted to RERA for payment to the respondent/allottee.
For Order
The Tribunal noted a pending refund of Rs. 3,02,756/- and directed the matter to be listed on 24.10.2024, with instructions for the Office to submit a fresh report.
For Order
The Tribunal directed the Registry to report on the status of pending funds totaling Rs 3,02,756/- that need to be remitted from the UP REAT account to the U.P. Real Estate Regulatory Authority.
For Order
The Tribunal directed the office to report on the remaining 70% of the deposited amount (Rs 3,02,756/-) requested for release by the respondent and scheduled the matter for consideration on 23-09-2024.
Tribunal Order #0901126035222024-01-10-2024
The Tribunal noted a pending refund of Rs. 3,02,756/- and directed the matter to be listed on 24.10.2024, with instructions for the Office to submit a fresh report.
Tribunal Order #0901126035222024-11-09-2024
The Tribunal directed the office to report on the remaining 70% of the deposited amount (Rs 3,02,756/-) requested for release by the respondent and scheduled the matter for consideration on 23-09-2024.
Tribunal Order #0901126035222024-24-10-2024
The Tribunal allowed the application to correct a previous order, directing that the remaining amount of Rs. 3,02,756/- be remitted to RERA for payment to the respondent/allottee.
Tribunal Order #0901126035222024-23-09-2024
The Tribunal directed the Registry to report on the status of pending funds totaling Rs 3,02,756/- that need to be remitted from the UP REAT account to the U.P. Real Estate Regulatory Authority.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the application to correct a previous order, directing that the remaining amount of Rs. 3,02,756/- be remitted to RERA for payment to the respondent/allottee. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the application to correct a previous order, directing that the remaining amount of Rs. 3,02,756/- be remitted to RERA for payment to the respondent/allottee.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (4)
The Tribunal noted a pending refund of Rs. 3,02,756/- and directed the matter to be listed on 24.10.2024, with instructions for the Office to submit a fresh report.
The Tribunal directed the office to report on the remaining 70% of the deposited amount (Rs 3,02,756/-) requested for release by the respondent and scheduled the matter for consideration on 23-09-2024.
The Tribunal allowed the application to correct a previous order, directing that the remaining amount of Rs. 3,02,756/- be remitted to RERA for payment to the respondent/allottee.
The Tribunal directed the Registry to report on the status of pending funds totaling Rs 3,02,756/- that need to be remitted from the UP REAT account to the U.P. Real Estate Regulatory Authority.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.