up_reraStatus: Completed
CASE ID: 0901126035132024

Appellant / Complainant

Satish Chandra Bajpai

VS

Respondent

U.P. State Industrial Development Corporation Limited

Developer Firm

u.p. state industrial development corporation limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126035132024 by Satish Chandra Bajpai against U.P. State Industrial Development Corporation Limited before up_rera.

2
Stage 129/07/2025

Delay condonation

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and consequently dismissed the appeal, finding the 417-day delay to be willful and lacking sufficient cause.

3
Stage 208/07/2025

Delay condonation

The Tribunal granted a 10-day extension to the respondent to file objections to the better affidavit and scheduled the appeal for hearing on 29.07.2025.

4
Stage 308/05/2025

Delay condonation

The Tribunal granted the appellant additional time to file a better affidavit in support of their delay condonation application and scheduled the next hearing for July 8, 2025.

5
Stage 424/04/2025

Delay condonation

The Tribunal granted adjournment applications filed by both parties and rescheduled the appeal for hearing on 08.05.2025.

6
Stage 527/03/2025

Delay condonation

The Tribunal granted the appellant additional time to file a better affidavit in support of their application for condonation of delay and scheduled the matter for hearing on 24.04.2025.

7
Stage 621/02/2025

Delay condonation

The Tribunal granted the respondent/promoter additional time to file objections and adjourned the appeal to March 27, 2025.

8
Stage 706/02/2025

Delay condonation

The Tribunal has ordered that Appeal-323/2024 be listed alongside Appeal No. 674 of 2023 for orders on 21.02.2025.

9
Stage 815/01/2025

Delay condonation

The Tribunal noted the filing of the affidavit of service and directed the respondent to file objections, scheduling the appeal for a hearing on 06.02.2025.

10
Stage 911/12/2024

Delay condonation

The Tribunal has scheduled the appeal for a hearing on 15.01.2025 and directed that any objections be filed in the interim.

11
Stage 1013/11/2024

Delay condonation

This is a procedural order referring the parties to a previous order passed in Appeal No. D 51/2024.

12
Stage 1116/10/2024

Delay condonation

The Tribunal listed the defective appeal for consideration regarding the application for condonation of delay on 13.11.2024.

13
Stage 1210/09/2024

Delay condonation

The Tribunal issued notice to the respondent and provided specific procedural directions for the service of notice and filing of objections regarding the application for condonation of delay.

14
Stage 13Final Ruling Order

Tribunal Order #0901126035132024-29-07-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and consequently dismissed the appeal, finding the 417-day delay to be willful and lacking sufficient cause.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and consequently dismissed the appeal, finding the 417-day delay to be willful and lacking sufficient cause. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and consequently dismissed the appeal, finding the 417-day delay to be willful and lacking sufficient cause.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Deepak Dwivedi

Respondent Advocate(s)

  • Suchita Singh
  • Sanjeev Singh

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126035132024-29-07-2025

The U.P. Real Estate Appellate Tribunal rejected the application for condonation of delay and consequently dismissed the appeal, finding the 417-day delay to be willful and lacking sufficient cause.

TathyaGrid RERA Intelligence AI

Need to research all rulings for u.p. state industrial development corporation limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.