up_reraStatus: Completed
CASE ID: 0901126035102024

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Srishti Singh

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Non-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126035102024 by Lucknow Development Authority against Srishti Singh before up_rera.

Non-Compliance & Execution
2
Stage 104/07/2025

for delivery of Judgment/Order

The Tribunal rejected the application for condonation of delay and the subsequent recall application filed by the Lucknow Development Authority, ruling that the 462-day delay was not sufficiently explained.

3
Stage 215/05/2025

Hearing on Recall App

The Tribunal heard arguments from the counsel for both parties regarding an application and its objections, but has reserved the order for a later date.

4
Stage 305/05/2025

Hearing on Recall App

The matter was adjourned to 15.05.2025 due to the unavailability of the portal.

5
Stage 410/04/2025

Hearing on Recall App

The Tribunal granted a request for adjournment on behalf of the respondent's counsel and rescheduled the case for hearing on 05.05.2025.

6
Stage 510/03/2025

Hearing on Recall App

The Tribunal has granted a request to adjourn the matter and rescheduled the hearing for April 10, 2025.

7
Stage 607/02/2025

Hearing on Recall App

The appeal has been adjourned at the request of the applicant's counsel and is scheduled to be listed on 27.02.2025.

8
Stage 722/01/2025

Hearing on Recall App

The Tribunal granted the appellant seven days to file a rejoinder affidavit regarding the respondent's objection and scheduled the matter for orders on February 7, 2025.

9
Stage 807/01/2025

Hearing on Recall App

The Tribunal granted a request for adjournment and rescheduled the matter to 22.01.2025, noting that no further adjournments will be permitted.

10
Stage 903/12/2024

Hearing on Recall App

The Tribunal granted the respondent one week to file objections to a recall application and directed the applicant to reply thereafter, scheduling the matter for consideration on 07.01.2025.

11
Stage 1025/10/2024

Hearing on Recall App

The Tribunal directed the respondent to file objections to the application for condonation of delay within two weeks and instructed the appellant to reply thereafter, scheduling the matter for orders on 03.12.2024.

12
Stage 1127/09/2024

Hearing on Recall App

The Tribunal granted the respondent 10 days to file objections to a recall application and directed the applicant to file a reply within 7 days of receiving those objections, scheduling the next hearing for October 25, 2024.

13
Stage 1211/09/2024

Hearing on Recall App

The Tribunal issued notice to the respondent regarding the Lucknow Development Authority's application to condone delay and recall a dismissal order, scheduling the matter for hearing on 27.09.2024.

14
Stage 13Final Ruling Order

Tribunal Order #0901126035102024-04-07-2025

The Tribunal rejected the application for condonation of delay and the subsequent recall application filed by the Lucknow Development Authority, ruling that the 462-day delay was not sufficiently explained.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the application for condonation of delay and the subsequent recall application filed by the Lucknow Development Authority, ruling that the 462-day delay was not sufficiently explained. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the application for condonation of delay and the subsequent recall application filed by the Lucknow Development Authority, ruling that the 462-day delay was not sufficiently explained.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Vasudev Trivedi
  • Abhishek Khare
  • Amit Yadav

Respondent Advocate(s)

  • Saghar Mehdi

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126035102024-04-07-2025

The Tribunal rejected the application for condonation of delay and the subsequent recall application filed by the Lucknow Development Authority, ruling that the 462-day delay was not sufficiently explained.