up_reraStatus: Completed
CASE ID: 0901126035052021

Appellant / Complainant

Neelam Jain

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

19 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126035052021 by Neelam Jain against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.

3
Stage 222/12/2022

Hearing

The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.

4
Stage 321/12/2022

Hearing

Upon the joint request of the counsels for both parties, the appeal has been adjourned and listed for further orders on 22.12.2022.

5
Stage 414/09/2022

Part Heard

The court heard arguments from both parties and reserved the judgment for a later date.

6
Stage 530/08/2022

Hearing

The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for September 14, 2022.

7
Stage 601/08/2022

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 30.08.2022.

8
Stage 723/05/2022

Hearing

The Tribunal directed the parties to exchange a list of dates and case citations via email at least seven days before the next hearing, which is scheduled for August 1, 2022.

9
Stage 819/04/2022

Hearing

The Tribunal granted an adjournment requested by the respondent and rescheduled the hearing for May 23, 2022.

10
Stage 925/02/2022

Hearing

The case was adjourned because no one appeared on behalf of the appellant; the matter is rescheduled for hearing on 19.04.2022.

11
Stage 1017/01/2022

Delay condonation

No text available.

12
Stage 1117/12/2021

Delay condonation

The Tribunal granted the respondent a short adjournment to file a reply to the grounds of appeal and scheduled the next hearing for 17.01.2022.

13
Stage 1223/11/2021

Notice

The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.

14
Stage 1329/09/2021

Notice

The Tribunal directed the appellant to re-send notice to the Lucknow Development Authority with complete details and ordered the respondent to file its Vakalatnama and objection to the limitation application by 23.11.2021.

15
Stage 1409/09/2021

Delay condonation

The Tribunal noted that the appeal was filed beyond the prescribed limitation period and issued notice to the respondent, scheduling the matter for September 29, 2021, to address the limitation application.

16
Stage 15Final Ruling Order

Tribunal Order #0901126035052021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.

17
Stage 16Interim Order

Tribunal Order #0901126035052021-22-12-2022

The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.

18
Stage 17Interim Order

Tribunal Order #0901126035052021-23-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126035052021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.

INTERIM_ORDEROrder ID: 0901126035052021-22-12-2022

The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.

INTERIM_ORDEROrder ID: 0901126035052021-23-11-2021

The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.