Appellant / Complainant
Neelam Jain
Respondent
Lucknow Development Authority
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126035052021 by Neelam Jain against Lucknow Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.
Hearing
The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.
Hearing
Upon the joint request of the counsels for both parties, the appeal has been adjourned and listed for further orders on 22.12.2022.
Part Heard
The court heard arguments from both parties and reserved the judgment for a later date.
Hearing
The Tribunal granted an adjournment application filed by the respondent's counsel and rescheduled the hearing for September 14, 2022.
Hearing
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 30.08.2022.
Hearing
The Tribunal directed the parties to exchange a list of dates and case citations via email at least seven days before the next hearing, which is scheduled for August 1, 2022.
Hearing
The Tribunal granted an adjournment requested by the respondent and rescheduled the hearing for May 23, 2022.
Hearing
The case was adjourned because no one appeared on behalf of the appellant; the matter is rescheduled for hearing on 19.04.2022.
Delay condonation
The Tribunal granted the respondent a short adjournment to file a reply to the grounds of appeal and scheduled the next hearing for 17.01.2022.
Notice
The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.
Notice
The Tribunal directed the appellant to re-send notice to the Lucknow Development Authority with complete details and ordered the respondent to file its Vakalatnama and objection to the limitation application by 23.11.2021.
Delay condonation
The Tribunal noted that the appeal was filed beyond the prescribed limitation period and issued notice to the respondent, scheduling the matter for September 29, 2021, to address the limitation application.
Tribunal Order #0901126035052021-30-12-2022
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.
Tribunal Order #0901126035052021-22-12-2022
The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.
Tribunal Order #0901126035052021-23-11-2021
The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.
Tribunal Disposal & Final Award Ruling
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.
Ruling Awarded To
Respondent
Interest Period
from 27.04.2013 to 26.10.2016
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Atul Tripathi
Respondent Advocate(s)
- Amit Yadav
Official RERA Tribunal Orders (3)
The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016 upon request. Additionally, it directed the transfer of funds deposited under Section 43(5) of the Act to the Regulatory Authority.
The Tribunal heard arguments from both counsels and scheduled the appeal for the delivery of judgment on December 30, 2022.
The Tribunal allowed the application for condonation of delay in filing the appeal due to the COVID-19 pandemic and directed the respondent to file a reply to the grounds of appeal.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.