up_reraStatus: Completed
CASE ID: 0901126035032021

Appellant / Complainant

Himani Sanwal

VS

Respondent

Lucknow Development Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

20 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126035032021 by Himani Sanwal against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/12/2022

for delivery of Judgment/Order

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

3
Stage 214/12/2022

Final Hearing

The Tribunal adjourned the appeal due to the absence of the appellant's counsel and scheduled the matter for hearing on 11.01.2023.

4
Stage 325/11/2022

Final Hearing

The Tribunal heard arguments from both parties and adjourned the appeal to 14.12.2022 for further arguments.

5
Stage 416/11/2022

Final Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on 25.11.2022.

6
Stage 520/10/2022

Final Hearing

The Tribunal granted adjournment applications filed by both parties and rescheduled the hearing for November 16, 2022.

7
Stage 619/09/2022

Hearing

The Tribunal granted a joint request from the parties to adjourn the appeal and listed it for hearing on 20.10.2022 along with cross Appeal No. (D) 31/2022.

8
Stage 722/08/2022

Hearing on Appeal

The court has scheduled the case for a hearing on 19.09.2022.

9
Stage 805/07/2022

Hearing on Appeal

The Tribunal granted a request from both counsels for an adjournment and rescheduled the hearing of the appeal to 22.08.2022.

10
Stage 928/04/2022

Hearing on Appeal

The Tribunal directed the parties to exchange and submit a list of dates, events, and relied-upon judgments within 20 days and scheduled the next hearing for July 5, 2022.

11
Stage 1015/04/2022

Hearing on Appeal

No text available.

12
Stage 1122/02/2022

Hearing on Appeal

The Tribunal directed the counsels for both parties to file and exchange a list of dates and events and listed the appeal for hearing on 15.04.2022.

13
Stage 1212/01/2022

Further Order

No text available.

14
Stage 1316/12/2021

Further Order

The Tribunal granted the respondent one week to file a reply to the grounds of appeal and directed that a copy be sent to the appellant via email before the next hearing.

15
Stage 1423/11/2021

Delay condonation

The Tribunal condoned a 3-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the respondent to file a reply before the next hearing on 16.12.2021.

16
Stage 1529/09/2021

Delay condonation

The Tribunal directed the appellant to re-send notice with correct officer details and scheduled the matter for 23.11.2021 to address a limitation application and the respondent's objection.

17
Stage 1609/09/2021

Delay condonation

The Tribunal issued notice to the respondent regarding a limitation issue and scheduled the matter for 29.09.2021 to dispose of the limitation application.

18
Stage 17Final Ruling Order

Tribunal Order #0901126035032021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

19
Stage 18Interim Order

Tribunal Order #0901126035032021-23-11-2021

The Tribunal condoned a 3-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the respondent to file a reply before the next hearing on 16.12.2021.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

Ruling Awarded To

Respondent

Interest Period

from 27.04.2013 to 26.10.2016

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Amit Yadav

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126035032021-30-12-2022

The Tribunal rejected the appeals filed by the Lucknow Development Authority and ruled that complainants are entitled to interest as compensation for the period from 27.04.2013 to 26.10.2016, upon request. Additionally, funds deposited under Section 43(5) of the Act are to be transferred to the Regulatory Authority for disposal.

INTERIM_ORDEROrder ID: 0901126035032021-23-11-2021

The Tribunal condoned a 3-day delay in filing the appeal by applying the Supreme Court's COVID-19 limitation relaxation and directed the respondent to file a reply before the next hearing on 16.12.2021.