Appellant / Complainant
Vikas Goel
Respondent
Yamuna Expressway Industrial Development Authority
Partial
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126034792023 by Vikas Goel against Yamuna Expressway Industrial Development Authority before up_rera.
Hearing
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the receipt of OC/CC or physical possession, whichever is later.
Hearing
The Tribunal refers the parties to a previous order passed in Appeal No. 180 of 2024 regarding the current matter.
Hearing
The Tribunal granted a request to list the appeal for orders on 20.01.2026, to be heard alongside Appeal No. 180 of 2024.
Hearing
The Tribunal granted a request for adjournment and rescheduled the appeal for hearing on 08.12.2025, to be heard alongside Appeal No. 180/2024.
Hearing
The Tribunal has scheduled the case for orders, to be heard alongside Appeal No. 180 of 2024, on November 18, 2025.
Hearing
The Tribunal granted the respondent ten days to upload relevant High Court and Supreme Court orders regarding injunctions and scheduled the next hearing for October 28, 2025.
Hearing
The Tribunal granted the respondent time to specify the force majeure period claimed due to court injunctions and directed them to record the date construction commenced. The matter is scheduled for hearing on 09.10.2025.
Hearing
Upon the joint request of the counsel for both parties, the Tribunal has adjourned the appeal and scheduled it for a new hearing date on 04.09.2025.
Hearing
The Tribunal granted a request from the appellant's counsel to reschedule the hearing, listing Appeal-557/2023 for 29.08.2025 alongside Appeal No. 180 of 2024.
Hearing
The Tribunal granted an adjournment request from the appellant's counsel and rescheduled the appeal for orders/hearing on 12.08.2024 at the request of the impleadment applicant.
Hearing
The Tribunal granted a joint request from the counsel for both parties to adjourn the appeal to 23.07.2025, noting that no further adjournments will be permitted.
Hearing
The Tribunal issued a show cause notice to the CEO of the respondent (YEIDA) regarding potential penal consequences under the Real Estate (Regulation and Development) Act, 2016, due to the failure to provide possession and the lack of an Occupancy Certificate/Completion Certificate.
Hearing
The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the hearing for May 7, 2025, to be heard alongside Cross Appeal No. 180/2024.
Hearing
Upon the joint request of the counsel for both parties, the tribunal has adjourned the appeal to be heard on 16.04.2025.
Hearing
The Tribunal granted a request from both counsels for more time and adjourned the matter to 20.03.2025, to be heard alongside cross appeal no. 180 of 2024.
Hearing
The Tribunal has adjourned the appeal to 27.02.2025 following a request from the learned counsels for both parties.
Hearing
The Tribunal has adjourned the appeal to 04.02.2025 for orders or hearing based on a joint request from both parties.
Delay condonation
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.
Delay condonation
The Tribunal adjourned the matter to 22.11.2024 upon the respondent's request and directed the parties to exchange pleadings in the interim.
Delay condonation
The Tribunal noted that pleadings have been exchanged and scheduled the appeal for hearing on 21.10.2024, to be heard alongside cross-appeal No. D 180/2024.
Delay condonation
The Tribunal granted an adjournment request and directed the respondent to file objections within 10 days, with the applicant permitted to file a reply thereafter. The matter is scheduled for hearing on 09.09.2024.
Delay condonation
The Tribunal granted the respondent one week's time to prepare their brief following the recent upload of the appellant's rejoinder and rescheduled the hearing to 08.08.2024.
Delay condonation
The Tribunal granted the appellant's counsel 10 days to file a reply to the respondent's objection and scheduled the matter for consideration of the condonation of delay application on 11.07.2024.
Delay condonation
The Tribunal granted extensions of time to both parties for filing replies and objections regarding the application for condonation of delay and the grounds of appeal, scheduling the next hearing for 14.05.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 12.04.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 07.03.2024.
Delay condonation
The Tribunal granted the respondent 10 days to file objections to the application for condonation of delay and the grounds of appeal, with the matter scheduled for hearing on 01.11.2023.
Delay condonation
The Tribunal issued a notice to the respondent regarding the application for condonation of delay and scheduled the matter for hearing on 20.09.2023.
Tribunal Order #0901126034792023-27-01-2026
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the receipt of OC/CC or physical possession, whichever is later.
Tribunal Order #0901126034792023-07-05-2025
The Tribunal issued a show cause notice to the CEO of the respondent (YEIDA) regarding potential penal consequences under the Real Estate (Regulation and Development) Act, 2016, due to the failure to provide possession and the lack of an Occupancy Certificate/Completion Certificate.
Tribunal Order #0901126034792023-04-09-2025
The Tribunal granted the respondent time to specify the force majeure period claimed due to court injunctions and directed them to record the date construction commenced. The matter is scheduled for hearing on 09.10.2025.
Tribunal Order #0901126034792023-22-11-2024
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.
Tribunal Disposal & Final Award Ruling
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the receipt of OC/CC or physical possession, whichever is later. Awarded in favor of Partial. Awarded interest rate: MCLR + 1 percent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the receipt of OC/CC or physical possession, whichever is later.
Ruling Awarded To
Partial
Awarded Interest Rate
MCLR + 1 percent
Interest Period
w.e.f. 21.11.2013 till obtaining OC/CC of the project or till handing over physical possession of the unit, whichever is later
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Deepti Mishra
Respondent Advocate(s)
- Hemant Tewari
- Fuhar Gupta
- Prashant Kumar
Official RERA Tribunal Orders (4)
The Tribunal disposed of the cross-appeals by applying the precedent set in Raj Kumar Goyal Vs. Yamuna Expressway Industrial Development Authority, ruling that the allottee is entitled to delay interest at MCLR+1 percent from 21.11.2013 until the receipt of OC/CC or physical possession, whichever is later.
The Tribunal issued a show cause notice to the CEO of the respondent (YEIDA) regarding potential penal consequences under the Real Estate (Regulation and Development) Act, 2016, due to the failure to provide possession and the lack of an Occupancy Certificate/Completion Certificate.
The Tribunal granted the respondent time to specify the force majeure period claimed due to court injunctions and directed them to record the date construction commenced. The matter is scheduled for hearing on 09.10.2025.
The Tribunal condoned the delay in filing the cross-appeals and directed the Registry to convert the defective appeal into a regular appeal, scheduling the hearing for January 7, 2025.