Appellant / Complainant
Gorakhpur Development Authority
Respondent
Ram Shankar Mishra
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126034512023 by Gorakhpur Development Authority against Ram Shankar Mishra before up_rera.
For Order
The Tribunal directed the transfer of the appellant's pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the respondent following the dismissal of the appeal for want of prosecution.
For Order
The Tribunal adjourned the proceedings due to a call for lawyers to abstain from judicial work by the Bar Council of Uttar Pradesh and rescheduled the matter for 13.10.2023.
For Order
The Tribunal issued notice to the appellant regarding an application for the release of deposited funds and directed specific procedural steps for service of notice and filing of objections before the next hearing on 05.09.2023.
Tribunal Order #0901126034512023-17-01-2024
The Tribunal directed the transfer of the appellant's pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the respondent following the dismissal of the appeal for want of prosecution.
Tribunal Disposal & Final Award Ruling
The Tribunal directed the transfer of the appellant's pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the respondent following the dismissal of the appeal for want of prosecution. Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal directed the transfer of the appellant's pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the respondent following the dismissal of the appeal for want of prosecution.
Ruling Awarded To
Respondent
Statutory Sections Cited (RERA Act 2016)
Official RERA Tribunal Orders (1)
The Tribunal directed the transfer of the appellant's pre-deposited amount under Section 43(5) to the U.P. Real Estate Regulatory Authority for disbursement to the respondent following the dismissal of the appeal for want of prosecution.