up_reraStatus: Completed
CASE ID: 0901126034372024

Appellant / Complainant

U.P. Awas Evam Vikas Parishad

VS

Respondent

Shailendra Pandey, Uttar Pradesh Real Estate Regulatory Authority

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

17 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126034372024 by U.P. Awas Evam Vikas Parishad against Shailendra Pandey, Uttar Pradesh Real Estate Regulatory Authority before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 108/10/2025

Delay condonation

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but, based on admitted facts and High Court precedent, ruled that the respondent is entitled to delay interest at MCLR+1% per annum for the period of delay.

3
Stage 208/09/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder and scheduled the appeal for hearing on 08.10.2025.

4
Stage 325/08/2025

Delay condonation

The Tribunal granted a request for adjournment on behalf of the appellant and scheduled the case for orders on 08.09.2025.

5
Stage 431/07/2025

Delay condonation

The Tribunal granted an adjournment requested by both parties due to illness and rescheduled the appeal for orders to 25.08.2025.

6
Stage 514/07/2025

Delay condonation

The Tribunal granted the appellant an additional three days to file a rejoinder affidavit and scheduled the next hearing for July 31, 2025.

7
Stage 621/05/2025

Delay condonation

The Tribunal granted the appellant 10 days to file a rejoinder affidavit and scheduled the case for orders on 14.07.2025.

8
Stage 729/04/2025

Delay condonation

The Tribunal has adjourned the matter to 21.05.2025 and permitted the filing of a rejoinder affidavit in the interim.

9
Stage 802/04/2025

Delay condonation

The Tribunal granted the appellant's counsel one week to file a rejoinder and scheduled the next hearing for April 29, 2025.

10
Stage 906/03/2025

Delay condonation

The Tribunal granted a request by the appellant's counsel to adjourn the appeal to 02.04.2025 and directed that a rejoinder to any objections be filed in the interim.

11
Stage 1012/02/2025

Delay condonation

The Tribunal has adjourned the appeal to 06.03.2025 and directed that pleadings be completed in the interim.

12
Stage 1123/01/2025

Delay condonation

The Tribunal has scheduled the appeal for a hearing on 12.02.2025 and directed the respondent to file any objections in the interim.

13
Stage 1218/12/2024

Delay condonation

The Tribunal has scheduled the appeal for a hearing on 23.01.2025 and directed the respondent to file their objections in the interim.

14
Stage 1321/11/2024

Delay condonation

The Tribunal granted the respondent 10 days to file objections, with the appellant permitted to file a reply within one week thereafter, and scheduled the matter for hearing on 18.12.2024.

15
Stage 1421/10/2024

Delay condonation

The Tribunal issued notice to the respondent regarding the delayed appeal and directed the appellant to serve the notice and appeal documents via post and email, scheduling the matter for 21.11.2024.

16
Stage 15Final Ruling Order

Tribunal Order #0901126034372024-08-10-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but, based on admitted facts and High Court precedent, ruled that the respondent is entitled to delay interest at MCLR+1% per annum for the period of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but, based on admitted facts and High Court precedent, ruled that the respondent is entitled to delay interest at MCLR+1% per annum for the period of delay. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: RespondentInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but, based on admitted facts and High Court precedent, ruled that the respondent is entitled to delay interest at MCLR+1% per annum for the period of delay.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% per annum

Interest Period

w.e.f. 29.09.2018 to 08.03.2021

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra
  • Gautam Johri

Respondent Advocate(s)

  • Pramod Mitra

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126034372024-08-10-2025

The Tribunal set aside the Adjudicating Officer's order due to lack of jurisdiction but, based on admitted facts and High Court precedent, ruled that the respondent is entitled to delay interest at MCLR+1% per annum for the period of delay.