up_reraStatus: Completed
CASE ID: 0901126034062023

Appellant / Complainant

Rajesh Arora, Veena Arora

VS

Respondent

Lucknow Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126034062023 by Rajesh Arora, Veena Arora against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 115/01/2025

For Order

The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.

3
Stage 203/09/2024

Hearing

The Tribunal heard arguments from both parties regarding the applicability of a previous judgment and a Supreme Court precedent, subsequently reserving the judgment for final delivery.

4
Stage 323/08/2024

Admission

The Tribunal granted a joint request from both parties to reschedule the hearing of the appeal to 03.09.2024.

5
Stage 414/08/2024

Admission

The Tribunal granted the respondent's application to recall an ex parte order dated 11.03.2024 and took the respondent's objections on record, subsequently adjourning the matter to 23.08.2024.

6
Stage 508/08/2024

Admission

The Tribunal granted a final opportunity to the respondent to argue their recall application regarding an ex parte proceeding and scheduled the matter for 14.08.2024.

7
Stage 622/07/2024

Admission

The Tribunal granted the respondent a final three-day opportunity to file their vakalatnama and scheduled the matter for orders on August 8, 2024.

8
Stage 722/05/2024

Admission

The Tribunal directed the respondent's counsel to file a Vakalatnama for previously filed objections and rescheduled the hearing to 22.07.2024.

9
Stage 807/05/2024

Admission

The Tribunal directed the respondent to serve a copy of their application for recall of the order dated 11.03.2024 to the appellants within 24 hours and scheduled the matter for further orders on 22.05.2024.

10
Stage 915/04/2024

Admission

The Tribunal noted the appellant's submission that the matter has proceeded ex-parte against the respondent and rescheduled the appeal for hearing/orders on 07.05.2024.

11
Stage 1011/03/2024

Admission

The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.

12
Stage 1101/02/2024

Admission

The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and a vakalatnama, with the matter scheduled for hearing on 11.03.2024.

13
Stage 1202/11/2023

Admission

No text available.

14
Stage 1320/09/2023

Admission

The Tribunal granted the respondent 10 days to file objections to the appeal and directed both parties to exchange documents via email and upload them to the e-portal before the next hearing on 02.11.2023.

15
Stage 1402/08/2023

Admission

The Tribunal issued a notice to the respondent (Lucknow Development Authority) and established a procedural timeline for service of appeal documents and filing of objections prior to the next hearing on 20.09.2023.

16
Stage 15Final Ruling Order

Tribunal Order #0901126034062023-15-01-2025

The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.

17
Stage 16Interim Order

Tribunal Order #0901126034062023-11-03-2024

The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

w.e.f. 15.09.2014 to 03.09.2022

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Harish Pandey
  • Isha Asthana

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126034062023-15-01-2025

The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.

INTERIM_ORDEROrder ID: 0901126034062023-11-03-2024

The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.