Appellant / Complainant
Rajesh Arora, Veena Arora
Respondent
Lucknow Development Authority
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126034062023 by Rajesh Arora, Veena Arora against Lucknow Development Authority before up_rera.
For Order
The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.
Hearing
The Tribunal heard arguments from both parties regarding the applicability of a previous judgment and a Supreme Court precedent, subsequently reserving the judgment for final delivery.
Admission
The Tribunal granted a joint request from both parties to reschedule the hearing of the appeal to 03.09.2024.
Admission
The Tribunal granted the respondent's application to recall an ex parte order dated 11.03.2024 and took the respondent's objections on record, subsequently adjourning the matter to 23.08.2024.
Admission
The Tribunal granted a final opportunity to the respondent to argue their recall application regarding an ex parte proceeding and scheduled the matter for 14.08.2024.
Admission
The Tribunal granted the respondent a final three-day opportunity to file their vakalatnama and scheduled the matter for orders on August 8, 2024.
Admission
The Tribunal directed the respondent's counsel to file a Vakalatnama for previously filed objections and rescheduled the hearing to 22.07.2024.
Admission
The Tribunal directed the respondent to serve a copy of their application for recall of the order dated 11.03.2024 to the appellants within 24 hours and scheduled the matter for further orders on 22.05.2024.
Admission
The Tribunal noted the appellant's submission that the matter has proceeded ex-parte against the respondent and rescheduled the appeal for hearing/orders on 07.05.2024.
Admission
The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.
Admission
The Tribunal granted the respondent 10 days to file objections to the grounds of appeal and a vakalatnama, with the matter scheduled for hearing on 11.03.2024.
Admission
The Tribunal granted the respondent 10 days to file objections to the appeal and directed both parties to exchange documents via email and upload them to the e-portal before the next hearing on 02.11.2023.
Admission
The Tribunal issued a notice to the respondent (Lucknow Development Authority) and established a procedural timeline for service of appeal documents and filing of objections prior to the next hearing on 20.09.2023.
Tribunal Order #0901126034062023-15-01-2025
The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.
Tribunal Order #0901126034062023-11-03-2024
The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.
Tribunal Disposal & Final Award Ruling
The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f. 15.09.2014 to 03.09.2022
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Harish Pandey
- Isha Asthana
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (2)
The Tribunal allowed the appeal and modified the RERA Authority's order, ruling that the removal of high-tension electric wires does not constitute 'force majeure' and directing the respondent to pay interest at MCLR+1% from 15.09.2014 to 03.09.2022.
The Tribunal has decided to proceed ex parte against the respondent, Lucknow Development Authority, due to their repeated failure to file objections despite being granted multiple extensions. The matter is listed for an ex parte hearing on 15.04.2024.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.