Appellant / Complainant
Bhupendra Singh
Respondent
UP Avas Evam Vikas Parishad
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126033912023 by Bhupendra Singh against UP Avas Evam Vikas Parishad before up_rera.
Hearing
The Tribunal set aside the Regulatory Authority's order, ruling that executing a sale deed or taking possession does not waive an allottee's statutory right to claim interest for project delays under Section 18 of the Act. The Respondent is directed to pay interest at MCLR+1% for the delay period from 01.03.2015 to 28.02.2019 within 45 days.
Hearing
The Tribunal granted the appellant time to prepare arguments following the filing of a rejoinder and scheduled the appeal for final hearing on 17.10.2024.
Hearing
The Tribunal granted the appellant seven days to file a reply to the respondent's objections and scheduled the next hearing for September 9, 2024.
Hearing
The Tribunal granted the appellant one week to file a rejoinder to the respondent's objections and scheduled the matter for hearing on 07.08.2024.
Hearing
The Tribunal granted a final 10-day extension to the respondent for filing objections and directed the exchange of documents via email before the next hearing on July 11, 2024.
Admission
The Tribunal granted a 10-day extension to the respondent for filing objections due to an adjournment request by the appellant's counsel and scheduled the next hearing for May 14, 2024.
Admission
The Tribunal has ordered the appeal to be listed for admission on 12.04.2024.
Admission
The Tribunal closed the respondent's opportunity to file objections due to their failure to appear or respond despite sufficient notice and automated digital communication. The matter is scheduled for hearing on 03.04.2024.
Admission
The Tribunal treated the service of notice on the respondent as sufficient and granted a 10-day extension for filing objections, with the next hearing scheduled for 06.03.2024.
Admission
The Tribunal granted the appellant three days to file a transaction report proving service of notice via email and scheduled the matter for orders on 29.01.2024.
Admission
The Tribunal granted the appellant seven days to file an affidavit of service and scheduled the appeal for hearing on 03.10.2023.
Admission
The Tribunal issued a notice to the respondent and outlined specific procedural instructions for the appellant regarding service of process via speed-post and email.
Tribunal Order #0901126033912023-06-03-2024
The Tribunal closed the respondent's opportunity to file objections due to their failure to appear or respond despite sufficient notice and automated digital communication. The matter is scheduled for hearing on 03.04.2024.
Tribunal Order #0901126033912023-17-10-2024
The Tribunal set aside the Regulatory Authority's order, ruling that executing a sale deed or taking possession does not waive an allottee's statutory right to claim interest for project delays under Section 18 of the Act. The Respondent is directed to pay interest at MCLR+1% for the delay period from 01.03.2015 to 28.02.2019 within 45 days.
Tribunal Disposal & Final Award Ruling
The Tribunal set aside the Regulatory Authority's order, ruling that executing a sale deed or taking possession does not waive an allottee's statutory right to claim interest for project delays under Section 18 of the Act. The Respondent is directed to pay interest at MCLR+1% for the delay period from 01.03.2015 to 28.02.2019 within 45 days. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal set aside the Regulatory Authority's order, ruling that executing a sale deed or taking possession does not waive an allottee's statutory right to claim interest for project delays under Section 18 of the Act. The Respondent is directed to pay interest at MCLR+1% for the delay period from 01.03.2015 to 28.02.2019 within 45 days.
Ruling Awarded To
Appellant
Awarded Interest Rate
MCLR+1%
Interest Period
from 01.03.2015 to 28.02.2019
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- V.K Singh
Respondent Advocate(s)
- Nn Pandey
Official RERA Tribunal Orders (2)
The Tribunal closed the respondent's opportunity to file objections due to their failure to appear or respond despite sufficient notice and automated digital communication. The matter is scheduled for hearing on 03.04.2024.
The Tribunal set aside the Regulatory Authority's order, ruling that executing a sale deed or taking possession does not waive an allottee's statutory right to claim interest for project delays under Section 18 of the Act. The Respondent is directed to pay interest at MCLR+1% for the delay period from 01.03.2015 to 28.02.2019 within 45 days.