up_reraStatus: Completed
CASE ID: 0901126033832024

Appellant / Complainant

Eureka Builders Private Limited

VS

Respondent

Pragati Gupta

Developer Firm

eureka builders private limited

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

12 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126033832024 by Eureka Builders Private Limited against Pragati Gupta before up_rera.

2
Stage 104/03/2025

Delay condonation

The Tribunal allowed the appellant's application to withdraw the appeal and directed that the amount deposited by the promoter under Section 43(5) of the Act be released to the respondent-allottee following due process.

3
Stage 210/02/2025

Delay condonation

The Appellant submitted that they have complied with the previous order by recalling the demand notice dated 18.07.2023 and communicating this to the Respondent; the matter is scheduled for final hearing on 04.03.2025.

4
Stage 306/01/2025

Delay condonation

The Appellant (Eureka Builders Private Limited) has undertaken to withdraw its demand notice dated 18.07.2023, which the Tribunal has accepted and recorded.

5
Stage 405/12/2024

Delay condonation

The Tribunal adjourned the appeal to 06.01.2025 and granted the appellant permission to file a rejoinder in the interim.

6
Stage 504/11/2024

Delay condonation

The Tribunal noted that advocates were abstaining from judicial work due to a Bar Council resolution and subsequently listed the appeal for hearing on 05.12.2024.

7
Stage 624/09/2024

Delay condonation

The Tribunal issued notice to the respondent regarding an appeal against orders passed by the Regular Authority and directed the applicant to comply with service protocols for the application for condonation of delay. The matter is listed for hearing on 04.11.2024.

8
Stage 7Final Ruling Order

Tribunal Order #0901126033832024-04-03-2025

The Tribunal allowed the appellant's application to withdraw the appeal and directed that the amount deposited by the promoter under Section 43(5) of the Act be released to the respondent-allottee following due process.

9
Stage 8Interim Order

Tribunal Order #0901126033832024-24-09-2024

The Tribunal issued notice to the respondent regarding an appeal against orders passed by the Regular Authority and directed the applicant to comply with service protocols for the application for condonation of delay. The matter is listed for hearing on 04.11.2024.

10
Stage 9Interim Order

Tribunal Order #0901126033832024-10-02-2025

The Appellant submitted that they have complied with the previous order by recalling the demand notice dated 18.07.2023 and communicating this to the Respondent; the matter is scheduled for final hearing on 04.03.2025.

11
Stage 10Interim Order

Tribunal Order #0901126033832024-06-01-2025

The Appellant (Eureka Builders Private Limited) has undertaken to withdraw its demand notice dated 18.07.2023, which the Tribunal has accepted and recorded.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal allowed the appellant's application to withdraw the appeal and directed that the amount deposited by the promoter under Section 43(5) of the Act be released to the respondent-allottee following due process. Awarded in favor of Respondent.

Disposal Winner: RespondentStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal allowed the appellant's application to withdraw the appeal and directed that the amount deposited by the promoter under Section 43(5) of the Act be released to the respondent-allottee following due process.

Ruling Awarded To

Respondent

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Siddharth Nandwani

Respondent Advocate(s)

  • Tushar Manjhwar
  • Vineet Kumar

Official RERA Tribunal Orders (4)

FINAL_ORDEROrder ID: 0901126033832024-04-03-2025

The Tribunal allowed the appellant's application to withdraw the appeal and directed that the amount deposited by the promoter under Section 43(5) of the Act be released to the respondent-allottee following due process.

INTERIM_ORDEROrder ID: 0901126033832024-24-09-2024

The Tribunal issued notice to the respondent regarding an appeal against orders passed by the Regular Authority and directed the applicant to comply with service protocols for the application for condonation of delay. The matter is listed for hearing on 04.11.2024.

INTERIM_ORDEROrder ID: 0901126033832024-10-02-2025

The Appellant submitted that they have complied with the previous order by recalling the demand notice dated 18.07.2023 and communicating this to the Respondent; the matter is scheduled for final hearing on 04.03.2025.

INTERIM_ORDEROrder ID: 0901126033832024-06-01-2025

The Appellant (Eureka Builders Private Limited) has undertaken to withdraw its demand notice dated 18.07.2023, which the Tribunal has accepted and recorded.

TathyaGrid RERA Intelligence AI

Need to research all rulings for eureka builders private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →