up_reraStatus: Completed
CASE ID: 0901126032582022

Appellant / Complainant

Om Prakash Garg and Sons HUF

VS

Respondent

LR Infrahomes (India) Private Limited

Developer Firm

lr infrahomes (india) private limited

Disputed Amount

28,80,000

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / Interest

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

33 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126032582022 by Om Prakash Garg and Sons HUF against LR Infrahomes (India) Private Limited before up_rera.

Delay in PossessionDelay Compensation / Interest
2
Stage 130/07/2025

Hearing

The U.P. Real Estate Appellate Tribunal modified the previous UP RERA order to grant the appellant delay interest at MCLR+1% effective from 01.03.2017 until possession, based on the terms of the Builder Buyer Agreement.

3
Stage 210/07/2025

Hearing

The Tribunal allowed an amendment application (IA No. 333 of 2025) and granted the respondent 10 days to file objections, scheduling the case for orders on 30.07.2025.

4
Stage 319/05/2025

Hearing

Upon the joint request of the counsel for both parties, the appeal has been adjourned and listed for hearing on 10.07.2025.

5
Stage 417/01/2025

Hearing

The appeal was dismissed for want of prosecution as no one appeared to press the matter.

6
Stage 516/12/2024

Hearing

The Tribunal granted a request for adjournment submitted by the appellant's counsel and rescheduled the appeal for hearing on 17.01.2025.

7
Stage 613/11/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and rescheduled the hearing for December 16, 2024.

8
Stage 704/10/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and rescheduled the appeal for final hearing on 13.11.2024.

9
Stage 803/09/2024

Hearing

The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the matter for orders on 04.10.2024.

10
Stage 901/08/2024

Hearing

No text available.

11
Stage 1004/07/2024

Hearing

Upon the joint request of the counsel for both parties, the matter has been adjourned and listed for hearing on 01.08.2024.

12
Stage 1106/05/2024

Hearing

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing for July 4, 2024.

13
Stage 1204/04/2024

Hearing

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing for May 6, 2024.

14
Stage 1301/03/2024

Hearing

The Tribunal has ordered the appeal to be listed for a hearing on 04.04.2024.

15
Stage 1422/01/2024

Hearing

The U.P. Real Estate Appellate Tribunal has scheduled the appeal for a hearing on March 1, 2024.

16
Stage 1518/10/2023

Hearing

No text available.

17
Stage 1612/09/2023

Hearing

No text available.

18
Stage 1724/07/2023

Hearing

No text available.

19
Stage 1811/05/2023

Hearing

No text available.

20
Stage 1929/03/2023

Delay condonation

The Tribunal granted a request for adjournment from both parties and rescheduled the hearing for May 11, 2023.

21
Stage 2023/02/2023

Hearing

The Tribunal adjourned the proceedings due to the respondent's counsel being on leave and directed the Registrar to ensure the conversion of the case from a defective appeal to a regular appeal as previously ordered.

22
Stage 2123/01/2023

Hearing

No text available.

23
Stage 2215/12/2022

Hearing

The Tribunal granted the appellant one week to file a reply to the respondent's objections and set a timeline for the exchange of documents via email, scheduling the next hearing for 23.01.2023.

24
Stage 2321/11/2022

Hearing

No text available.

25
Stage 2414/10/2022

Hearing

No text available.

26
Stage 2515/09/2022

Hearing

No text available.

27
Stage 2623/08/2022

Hearing

The Tribunal granted the respondent two days to file objections to the grounds of appeal and directed the parties to exchange copies via email and upload documents to the e-portal, with the matter listed for hearing on 15.09.2022.

28
Stage 2722/07/2022

Hearing

The Tribunal granted an adjournment requested by the respondent due to medical exigency and directed the parties to exchange objections and replies via email within specified timelines before the next hearing on 23.08.2022.

29
Stage 2830/06/2022

Defect Removal

The Tribunal disposed of the application for condonation of delay, finding the appeal was filed within the limitation period following the rejection of a rectification application, and directed the Registry to convert the defective appeal into a regular appeal.

30
Stage 29Final Ruling Order

Tribunal Order #0901126032582022-30-07-2025

The U.P. Real Estate Appellate Tribunal modified the previous UP RERA order to grant the appellant delay interest at MCLR+1% effective from 01.03.2017 until possession, based on the terms of the Builder Buyer Agreement.

31
Stage 30Interim Order

Tribunal Order #0901126032582022-30-06-2022

The Tribunal disposed of the application for condonation of delay, finding the appeal was filed within the limitation period following the rejection of a rectification application, and directed the Registry to convert the defective appeal into a regular appeal.

32
Stage 31Interim Order

Tribunal Order #0901126032582022-23-02-2023

The Tribunal adjourned the proceedings due to the respondent's counsel being on leave and directed the Registrar to ensure the conversion of the case from a defective appeal to a regular appeal as previously ordered.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The U.P. Real Estate Appellate Tribunal modified the previous UP RERA order to grant the appellant delay interest at MCLR+1% effective from 01.03.2017 until possession, based on the terms of the Builder Buyer Agreement. Awarded in favor of Appellant. Awarded interest rate: MCLR+1%.

Disposal Winner: AppellantInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The U.P. Real Estate Appellate Tribunal modified the previous UP RERA order to grant the appellant delay interest at MCLR+1% effective from 01.03.2017 until possession, based on the terms of the Builder Buyer Agreement.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR+1%

Interest Period

from 01.03.2017 till the date of handing over possession of the unit in habitable condition

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Tushar Bahadur
  • Sachin Gupta

Respondent Advocate(s)

  • Azhar Ikram
  • Manish Singh
  • Pranav Gupta

Official RERA Tribunal Orders (3)

FINAL_ORDEROrder ID: 0901126032582022-30-07-2025

The U.P. Real Estate Appellate Tribunal modified the previous UP RERA order to grant the appellant delay interest at MCLR+1% effective from 01.03.2017 until possession, based on the terms of the Builder Buyer Agreement.

INTERIM_ORDEROrder ID: 0901126032582022-30-06-2022

The Tribunal disposed of the application for condonation of delay, finding the appeal was filed within the limitation period following the rejection of a rectification application, and directed the Registry to convert the defective appeal into a regular appeal.

INTERIM_ORDEROrder ID: 0901126032582022-23-02-2023

The Tribunal adjourned the proceedings due to the respondent's counsel being on leave and directed the Registrar to ensure the conversion of the case from a defective appeal to a regular appeal as previously ordered.

TathyaGrid RERA Intelligence AI

Need to research all rulings for lr infrahomes (india) private limited?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →