Appellant / Complainant
Madhuri Verma, Dileep Kumar Verma
Respondent
Shalimar Corp Ltd.
shalimar corp ltd.
₹11,99,267
Respondent
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126031832022 by Madhuri Verma, Dileep Kumar Verma against Shalimar Corp Ltd. before up_rera.
For Order
The Tribunal dismissed the appeal, ruling that the allottee is not entitled to a refund for a delayed project once a Completion Certificate has been issued, but directed the respondent to refund the deposited amount minus 10% earnest money plus interest from April 23, 2022.
For Order
The Tribunal heard arguments from both parties regarding Appeal-385/2022 and has reserved the judgment for a later date.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel and scheduled the appeal for hearing on 10.07.2024.
For Order
The Tribunal directed the parties to produce the allotment letter/Builder Buyer Agreement (BBA) and ordered the respondent to explain the reasons for the cancellation of the appellant's unit.
For Order
The Tribunal granted an adjournment requested by the respondent's counsel to allow for further preparation and rescheduled the hearing for March 12, 2024.
Delay condonation
The Tribunal directed the respondent to explain why the remaining balance of the appellant's funds has not been released following unit cancellation and ordered the respondent to address the issue of interest payable on the withheld amount.
Delay condonation
The Tribunal granted an adjournment requested by the respondent's counsel due to illness and rescheduled the matter for 23.03.2023 to consider the application for condonation of delay.
Delay condonation
The Tribunal noted that no time remained for the hearing and ordered the defective appeal to be listed on 16.01.2023 for further orders.
Delay condonation
The Tribunal directed the Registry to register the appeal as a regular appeal and scheduled the matter for hearing on 08.12.2022.
Delay condonation
The Tribunal directed the respondent's counsel to rectify defects in the Vakalatnama within three days and ordered the applicant to file a replication/rejoinder against the respondent's reply before the next hearing on 13.10.2022.
Notice
The Tribunal directed the respondent to file objections against the grounds of appeal via email and scheduled the defective appeal for a hearing on September 8, 2022.
Defect Removal
The Tribunal issued notice to the respondent and directed the appellants to serve the appeal documents via speed-post and email, scheduling the next hearing for August 8, 2022.
Tribunal Order #0901126031832022-15-01-2025
The Tribunal dismissed the appeal, ruling that the allottee is not entitled to a refund for a delayed project once a Completion Certificate has been issued, but directed the respondent to refund the deposited amount minus 10% earnest money plus interest from April 23, 2022.
Tribunal Order #0901126031832022-23-03-2023
The Tribunal directed the respondent to explain why the remaining balance of the appellant's funds has not been released following unit cancellation and ordered the respondent to address the issue of interest payable on the withheld amount.
Tribunal Order #0901126031832022-12-03-2024
The Tribunal directed the parties to produce the allotment letter/Builder Buyer Agreement (BBA) and ordered the respondent to explain the reasons for the cancellation of the appellant's unit.
Tribunal Disposal & Final Award Ruling
The Tribunal dismissed the appeal, ruling that the allottee is not entitled to a refund for a delayed project once a Completion Certificate has been issued, but directed the respondent to refund the deposited amount minus 10% earnest money plus interest from April 23, 2022. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal dismissed the appeal, ruling that the allottee is not entitled to a refund for a delayed project once a Completion Certificate has been issued, but directed the respondent to refund the deposited amount minus 10% earnest money plus interest from April 23, 2022.
Ruling Awarded To
Respondent
Awarded Interest Rate
MCLR+1%
Interest Period
w.e.f. 23.04.2022 to the date of payment
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Manoj Kumar Srivastava
- Awadhesh Kumar Misra
Respondent Advocate(s)
- Anurag Singh
- Harit Mishra
Official RERA Tribunal Orders (3)
The Tribunal dismissed the appeal, ruling that the allottee is not entitled to a refund for a delayed project once a Completion Certificate has been issued, but directed the respondent to refund the deposited amount minus 10% earnest money plus interest from April 23, 2022.
The Tribunal directed the respondent to explain why the remaining balance of the appellant's funds has not been released following unit cancellation and ordered the respondent to address the issue of interest payable on the withheld amount.
The Tribunal directed the parties to produce the allotment letter/Builder Buyer Agreement (BBA) and ordered the respondent to explain the reasons for the cancellation of the appellant's unit.
Need to research all rulings for shalimar corp ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.