Appellant / Complainant
G.C. Construction and Developers Pvt. Ltd.
Respondent
Empire Estate Residency Welfare Society, Real Estate Regulatory Authority
g.c. construction and developers pvt. ltd.
Respondent
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126031682022 by G.C. Construction and Developers Pvt. Ltd. against Empire Estate Residency Welfare Society, Real Estate Regulatory Authority before up_rera.
Delay condonation
The U.P. Real Estate Appellate Tribunal allowed the appellant's request to withdraw the defective appeal (Appeal-474/2022), resulting in its dismissal as withdrawn.
Delay condonation
The Tribunal granted a final one-week extension to the respondent for filing objections at a cost of Rs. 5,000/- due to previous delays and non-compliance with prior orders.
Delay condonation
The Tribunal granted an adjournment to the respondent due to counsel's illness and provided a ten-day extension to file objections regarding the condonation of delay and grounds of appeal.
Delay condonation
The Tribunal granted a final 10-day extension to the respondent to file objections, warning that failure to comply will result in the right to file objections being closed and the matter proceeding ex-parte.
Notice
The Tribunal granted the respondent 10 days to file objections regarding the condonation of delay and grounds of appeal, with the matter scheduled for hearing on 30.09.2022.
Defect Removal
The Tribunal issued a notice to the respondent regarding an application for condonation of delay and set a hearing date for September 5, 2022, while outlining procedural steps for service of notice and filing objections.
Defect Removal
The Tribunal granted the appellant one week's time to place the execution proceedings before the RERA on record and scheduled the next hearing for 04.08.2022.
Tribunal Order #0901126031682022-07-12-2022
The Tribunal granted a final one-week extension to the respondent for filing objections at a cost of Rs. 5,000/- due to previous delays and non-compliance with prior orders.
Tribunal Disposal & Final Award Ruling
Dismissed as withdrawn Awarded in favor of Respondent.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
Dismissed as withdrawn
Ruling Awarded To
Respondent
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Anurag Singh
Respondent Advocate(s)
- Sandeep Srivastava
Official RERA Tribunal Orders (1)
The Tribunal granted a final one-week extension to the respondent for filing objections at a cost of Rs. 5,000/- due to previous delays and non-compliance with prior orders.
Need to research all rulings for g.c. construction and developers pvt. ltd.?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.