up_reraStatus: Completed
CASE ID: 0901126031522021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Mahendra Kumar Pandey

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

29 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126031522021 by Lucknow Development Authority against Mahendra Kumar Pandey before up_rera.

Delay in PossessionDelay Compensation / InterestStructural Defects & QualityJurisdiction & Maintainability
2
Stage 107/05/2024

for delivery of Judgment/Order

The Appellate Tribunal dismissed the appeals filed by the Lucknow Development Authority, upholding the Regulatory Authority's order for delay interest and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the respondents.

3
Stage 226/02/2024

Hearing

The Tribunal heard arguments from both parties regarding the challenge to a Regulatory Authority order and has reserved judgment for further consideration.

4
Stage 305/02/2024

Hearing

The Tribunal granted an adjournment requested by the appellant's counsel and scheduled the appeal for a hearing on 24.02.2024.

5
Stage 406/11/2023

Hearing

No text available.

6
Stage 522/09/2023

Hearing

The Tribunal noted the presence of the appellant's counsel and the absence of the respondent's counsel, subsequently scheduling the appeal for hearing on 06.11.2023.

7
Stage 607/08/2023

Hearing

No text available.

8
Stage 725/05/2023

Hearing

No text available.

9
Stage 827/04/2023

Hearing

The Tribunal noted that pleadings have been exchanged and scheduled the appeal for a hearing on May 25, 2023.

10
Stage 920/03/2023

Hearing

No text available.

11
Stage 1009/02/2023

Hearing

No text available.

12
Stage 1105/01/2023

Hearing

No text available.

13
Stage 1205/12/2022

Hearing

No text available.

14
Stage 1309/11/2022

For Order

The Tribunal granted an adjournment requested by the respondent's counsel due to illness and scheduled the appeal for hearing on 05.12.2022.

15
Stage 1428/09/2022

Further Order

This text represents the header/caption of an appeal (APPEAL-603/2021) before the U.P. Real Estate Appellate Tribunal involving Lucknow Development Authority and Mahendra Kumar Pandey; however, no substantive ruling or directive is contained in this excerpt.

16
Stage 1509/09/2022

Further Order

No text available.

17
Stage 1617/08/2022

Further Order

The Tribunal noted that pleadings have been exchanged and the case is ready for hearing; consequently, the matter is scheduled for a hearing on 09.09.2022.

18
Stage 1721/07/2022

Further Order

The Tribunal noted that the respondent's counsel is on leave and adjourned the appeal to 17.08.2022 for hearing.

19
Stage 1810/05/2022

Further Order

The Tribunal adjourned the case to 21.07.2022 due to lawyers abstaining from work following a resolution by the Oudh Bar Association.

20
Stage 1904/04/2022

Delay condonation

The Tribunal condoned the 366-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the defective appeal to be registered as a Regular Appeal.

21
Stage 2010/03/2022

Delay condonation

The Tribunal granted the appellant one week to file a better affidavit in support of their application for condonation of delay and scheduled the matter for hearing on 04.04.2022.

22
Stage 2105/01/2022

Delay condonation

The Tribunal adjourned the case to 28.01.2022 for the disposal of a limitation application and its corresponding objection.

23
Stage 2213/12/2021

Delay condonation

The Tribunal granted the respondent one week to file a Vakalatnama, objections to the delay condonation application, and a reply to the appeal, with the case scheduled for hearing on 05.01.2022.

24
Stage 2318/11/2021

Delay condonation

The Tribunal granted the respondent a final opportunity to engage counsel and noted that failure to appear at the next hearing will result in proceedings being initiated as per the Act. The matter is adjourned to 13.12.2021.

25
Stage 2426/10/2021

Delay condonation

The Tribunal noted the absence of the respondent's counsel and scheduled the case for 18.11.2021 to address the limitation application and any objections.

26
Stage 2522/09/2021

Delay condonation

The Tribunal issued notice to the respondent regarding the application for condonation of delay and directed the parties to exchange pleadings via email and e-portal before the next hearing on 26.10.2021.

27
Stage 26Final Ruling Order

Tribunal Order #0901126031522021-07-05-2024

The Appellate Tribunal dismissed the appeals filed by the Lucknow Development Authority, upholding the Regulatory Authority's order for delay interest and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the respondents.

28
Stage 27Interim Order

Tribunal Order #0901126031522021-04-04-2022

The Tribunal condoned the 366-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the defective appeal to be registered as a Regular Appeal.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Appellate Tribunal dismissed the appeals filed by the Lucknow Development Authority, upholding the Regulatory Authority's order for delay interest and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the respondents. Awarded in favor of Respondent. Awarded interest rate: SBI's MCLR+1% per annum.

Disposal Winner: RespondentInterest Rate: SBI's MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Appellate Tribunal dismissed the appeals filed by the Lucknow Development Authority, upholding the Regulatory Authority's order for delay interest and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the respondents.

Ruling Awarded To

Respondent

Awarded Interest Rate

SBI's MCLR+1% per annum

Interest Period

from 17.08.2017 till the date of Registry i.e. 13.09.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 14(3)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Harish Pandey

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126031522021-07-05-2024

The Appellate Tribunal dismissed the appeals filed by the Lucknow Development Authority, upholding the Regulatory Authority's order for delay interest and directing that the promoter's pre-deposited amount be transferred to U.P. RERA for disbursement to the respondents.

INTERIM_ORDEROrder ID: 0901126031522021-04-04-2022

The Tribunal condoned the 366-day delay in filing the appeal due to the COVID-19 pandemic period recognized by the Supreme Court and directed the defective appeal to be registered as a Regular Appeal.