up_reraStatus: Completed
CASE ID: 0901126031392022

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Geetanjali Mishra

Disposal Award

Respondent

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126031392022 by Lucknow Development Authority against Geetanjali Mishra before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 111/02/2025

Delay condonation

The Tribunal set aside the Adjudicating Officer's order for lack of jurisdiction but ruled that the appellant/promoter is mandatorily obligated to pay delay interest at MCLR+1% per annum to the respondent for the period from 05.10.2012 to 18.02.2019 (excluding a specific period of farmer agitation).

3
Stage 220/01/2025

For Order

The Tribunal granted a request for adjournment on behalf of the appellant and rescheduled the appeal for hearing on 11.02.2025, noting that no further adjournments will be permitted.

4
Stage 321/04/2023

Hearing

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority for want of prosecution due to the disengagement of its panel lawyers and failure to appear.

5
Stage 416/03/2023

Hearing

The Tribunal noted that the case is ripe for hearing and scheduled it for orders/hearing on 21.04.2023 following a request for adjournment by the respondent's counsel.

6
Stage 528/02/2023

Hearing

The Tribunal granted the applicant 10 days to file a reply to the respondent's objections and scheduled the appeal for a fresh hearing on March 16, 2023, following the departure of the previous presiding officer.

7
Stage 622/11/2022

Further Order

The court heard arguments from both the appellant and respondent and subsequently reserved the judgment for further delivery.

8
Stage 731/10/2022

Delay condonation

The Tribunal directed the Respondent to file a reply to the grounds of appeal and scheduled the defective appeal for further orders on 22.11.2022.

9
Stage 823/09/2022

Delay condonation

The Tribunal issued notice to the respondent and directed the applicant to serve the appeal documents via speed-post and email, scheduling the matter for 31.10.2022 to address the application for condonation of delay.

10
Stage 925/08/2022

Delay condonation

The Tribunal noted the respondent's absence despite service of notice and directed the appellant to file an affidavit of service, adjourning the defective appeal to 23.09.2022.

11
Stage 1029/07/2022

Delay condonation

No text available.

12
Stage 1104/07/2022

Defect Removal

The Tribunal granted three days to file a certified copy of the impugned order and issued notice to the respondent, returnable on 29.07.2022.

13
Stage 12Final Ruling Order

Tribunal Order #0901126031392022-11-02-2025

The Tribunal set aside the Adjudicating Officer's order for lack of jurisdiction but ruled that the appellant/promoter is mandatorily obligated to pay delay interest at MCLR+1% per annum to the respondent for the period from 05.10.2012 to 18.02.2019 (excluding a specific period of farmer agitation).

14
Stage 13Final Ruling Order

Tribunal Order #0901126031392022-21-04-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority for want of prosecution due to the disengagement of its panel lawyers and failure to appear.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order for lack of jurisdiction but ruled that the appellant/promoter is mandatorily obligated to pay delay interest at MCLR+1% per annum to the respondent for the period from 05.10.2012 to 18.02.2019 (excluding a specific period of farmer agitation). The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority for want of prosecution due to the disengagement of its panel lawyers and failure to appear. Awarded in favor of Respondent. Awarded interest rate: MCLR+1% per annum.

Disposal Winner: RespondentInterest Rate: MCLR+1% per annumStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order for lack of jurisdiction but ruled that the appellant/promoter is mandatorily obligated to pay delay interest at MCLR+1% per annum to the respondent for the period from 05.10.2012 to 18.02.2019 (excluding a specific period of farmer agitation). The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority for want of prosecution due to the disengagement of its panel lawyers and failure to appear.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1% per annum

Interest Period

from 05.10.2012 to 18.02.2019 (excluding period from 27.04.2013 to 26.10.2016)

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Abhishek Khare

Respondent Advocate(s)

  • Samarth Saxena

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126031392022-11-02-2025

The Tribunal set aside the Adjudicating Officer's order for lack of jurisdiction but ruled that the appellant/promoter is mandatorily obligated to pay delay interest at MCLR+1% per annum to the respondent for the period from 05.10.2012 to 18.02.2019 (excluding a specific period of farmer agitation).

FINAL_ORDEROrder ID: 0901126031392022-21-04-2023

The U.P. Real Estate Appellate Tribunal dismissed the appeal filed by the Lucknow Development Authority for want of prosecution due to the disengagement of its panel lawyers and failure to appear.