Appellant / Complainant
Ravi Verma, Vibha Verma
Respondent
Lucknow Development Authority
Appellant
Legal Issues & Claims Raised
Case Procedural History & Progression Tree
Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.
Complaint Filing & Dispute Registration
Complaint registered under Case ID 0901126030952024 by Ravi Verma, Vibha Verma against Lucknow Development Authority before up_rera.
for delivery of Judgment/Order
The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.
Further Hearing
The Tribunal heard arguments from various counsels representing the appellant and respondents, and subsequently reserved the judgment for delivery.
Further Hearing
The Tribunal has adjourned the matter and scheduled the appeal for further hearing on April 21, 2025, at 1:30 p.m.
Further Hearing
The Tribunal has adjourned the appeal to 11.04.2025 at 10:30 a.m. following a joint request from the counsel for both parties.
Hearing
The Tribunal refers the matter to the orders passed in Appeal No. D 220/2024 (Jitendra Kumar Shukla Vs. U.P. Avas Evam Vikas Parishad) for directions.
Admission
Upon the joint request of both parties, the matter has been adjourned and rescheduled for hearing on April 8, 2025, at 1:30 PM.
Admission
The Tribunal has scheduled the case for orders/hearing on 27.03.2025 before Court No. 1.
Admission
The Tribunal granted the respondent 10 days to file objections, with a provision for a rejoinder within one week thereafter, and scheduled the next hearing for March 26, 2025.
Admission
The Tribunal granted the respondent ten days to file objections to the grounds of appeal and directed the appellant to file a rejoinder within one week of receiving said objections.
Admission
The Tribunal issued notice to the respondent and directed the appellant to serve the notice and appeal documents via speed-post and email, scheduling the next hearing for February 6, 2025.
Tribunal Order #0901126030952024-29-08-2025
The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.
Tribunal Disposal & Final Award Ruling
The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds. Awarded in favor of Appellant.
Final Tribunal Order & Ruling Verdict Summary
Official Ruling Summary
The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.
Ruling Awarded To
Appellant
Interest Period
from the date of allotment/agreement till the date of offer of possession
Statutory Sections Cited (RERA Act 2016)
Appearing Legal Counsel & Advocates
Appellant Advocate(s)
- Atul Tripathi
Respondent Advocate(s)
- Abhishek Khare
Official RERA Tribunal Orders (1)
The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations by citing delay or the execution of conveyance deeds.
Need to research all rulings for a builder?
Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.