Legal Issues & Claims Raised

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

10 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030932023 by Galaxy International Realtech Pvt. Ltd. against Mahendra Kumar before up_rera.

Refund of InvestmentDelay Compensation / InterestNon-Compliance & Execution
2
Stage 113/05/2024

for delivery of Judgment/Order

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

3
Stage 208/05/2024

Defect Removal

The Tribunal heard arguments regarding the application for condonation of delay and has reserved its order on the matter.

4
Stage 305/04/2024

Defect Removal

The Tribunal decided to proceed ex-parte against the respondent due to non-appearance despite sufficient service of notice and scheduled an ex-parte hearing for May 8, 2024, regarding the application for condonation of delay.

5
Stage 401/03/2024

Defect Removal

The Tribunal has ordered the appeal to be listed for a hearing on 05.04.2024.

6
Stage 522/01/2024

Defect Removal

The Tribunal granted the respondent an additional 10 days to file objections and directed both parties to exchange documents electronically via email and the e-portal.

7
Stage 622/12/2023

Defect Removal

The Tribunal granted the appellant 24 hours to rectify reported procedural defects and directed the Registry to issue notice to the respondent for a hearing on January 22, 2024.

8
Stage 7Final Ruling Order

Tribunal Order #0901126030932023-13-05-2024

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

9
Stage 8Interim Order

Tribunal Order #0901126030932023-05-04-2024

The Tribunal decided to proceed ex-parte against the respondent due to non-appearance despite sufficient service of notice and scheduled an ex-parte hearing for May 8, 2024, regarding the application for condonation of delay.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee. Awarded in favor of Respondent. Awarded interest rate: MCLR+1%.

Disposal Winner: RespondentInterest Rate: MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

Ruling Awarded To

Respondent

Awarded Interest Rate

MCLR+1%

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 40Section 63Section 64

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Yash Tandon

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126030932023-13-05-2024

The Tribunal rejected the applicant's application for condonation of delay and dismissed the appeal, subsequently directing the transfer of the pre-deposited amount to U.P. RERA for disbursement to the allottee.

INTERIM_ORDEROrder ID: 0901126030932023-05-04-2024

The Tribunal decided to proceed ex-parte against the respondent due to non-appearance despite sufficient service of notice and scheduled an ex-parte hearing for May 8, 2024, regarding the application for condonation of delay.

TathyaGrid RERA Intelligence AI

Need to research all rulings for galaxy international realtech pvt. ltd.?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →