up_reraStatus: Completed
CASE ID: 0901126030922023

Appellant / Complainant

Hari Shyam Yadav

VS

Respondent

Ghaziabad Development Authority

Disputed Amount

24,13,079

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

18 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030922023 by Hari Shyam Yadav against Ghaziabad Development Authority before up_rera.

Delay in PossessionRefund of InvestmentDelay Compensation / InterestSale Deed & Title Transfer
2
Stage 107/03/2025

Hearing

The Tribunal set aside the Adjudicating Officer's order, ruling that the appellant is entitled to interest and compensation because the promoter failed to execute the conveyance deed after receiving the completion certificate, thereby constituting a failure to hand over possession.

3
Stage 213/02/2025

Hearing

The Tribunal has deferred the decision on whether the appellant is entitled to interest on a refunded amount and has scheduled the matter for further arguments on legal propositions on 07.03.2025.

4
Stage 313/01/2025

Hearing

No text available.

5
Stage 412/12/2024

Hearing

The Tribunal granted an adjournment requested by the appellant and rescheduled the hearing for January 13, 2025, noting that no further adjournments will be permitted.

6
Stage 506/11/2024

Hearing

The Tribunal condoned a 210-day delay in filing the appeal and directed the Registry to convert the defective appeal into a regular appeal, scheduling the next hearing for December 12, 2024.

7
Stage 616/10/2024

Hearing

The Tribunal granted a request from the respondent's counsel for time to attempt an out-of-court settlement and adjourned the matter to 06.11.2024.

8
Stage 709/09/2024

Hearing

The Tribunal granted the respondent seven days to upload documents including a brochure and completion certificate, with a directive to provide soft copies to the appellant, and scheduled the next hearing for 16.10.2024.

9
Stage 807/08/2024

Hearing

The Tribunal directed the respondent to provide copies of their objections to the appellant within three days, after which the appellant has seven days to file a reply; the matter is listed for hearing on 09.09.2024.

10
Stage 916/07/2024

For Order

The Tribunal granted the appellant a final opportunity to file a rejoinder against the respondent's objections within one week and scheduled the matter for hearing on 07.08.2024.

11
Stage 1016/05/2024

For Order

No text available.

12
Stage 1116/04/2024

Admission

The Tribunal granted the respondent 10 days to file a reply to objections and scheduled the appeal for hearing on 16.05.2024.

13
Stage 1212/03/2024

Admission

The Tribunal granted the respondent 10 days to file an objection and vakalatnama, directing that a soft copy be emailed to the appellant, with the matter listed for hearing on 16.04.2024.

14
Stage 1305/02/2024

Admission

The Tribunal treated the service of notice on the respondent as sufficient based on proof of delivery via email and speed post, while granting the respondent 10 days to file objections before proceeding ex-parte.

15
Stage 1406/11/2023

Admission

No text available.

16
Stage 1522/09/2023

Delay condonation

The Tribunal issued notice to the respondent regarding the applicant's application for condonation of delay and directed the applicant to serve the respondent via speed-post and email.

17
Stage 16Final Ruling Order

Tribunal Order #0901126030922023-07-03-2025

The Tribunal set aside the Adjudicating Officer's order, ruling that the appellant is entitled to interest and compensation because the promoter failed to execute the conveyance deed after receiving the completion certificate, thereby constituting a failure to hand over possession.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal set aside the Adjudicating Officer's order, ruling that the appellant is entitled to interest and compensation because the promoter failed to execute the conveyance deed after receiving the completion certificate, thereby constituting a failure to hand over possession. Awarded in favor of Appellant. Awarded interest rate: MCLR + 1%.

Disposal Winner: AppellantInterest Rate: MCLR + 1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal set aside the Adjudicating Officer's order, ruling that the appellant is entitled to interest and compensation because the promoter failed to execute the conveyance deed after receiving the completion certificate, thereby constituting a failure to hand over possession.

Ruling Awarded To

Appellant

Awarded Interest Rate

MCLR + 1%

Interest Period

till 20.10.2021 and on computed amount interest till the date of payment

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 11(4)(f)Section 17

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Applicant/Appellant In-Person

Respondent Advocate(s)

  • Rishabh Raj

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126030922023-07-03-2025

The Tribunal set aside the Adjudicating Officer's order, ruling that the appellant is entitled to interest and compensation because the promoter failed to execute the conveyance deed after receiving the completion certificate, thereby constituting a failure to hand over possession.