up_reraStatus: Completed
CASE ID: 0901126030802021

Appellant / Complainant

Lucknow Development Authority

VS

Respondent

Pushpa

Disputed Amount

26,30,000

Disposal Award

Partial

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestPromotional Misrepresentation

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

11 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030802021 by Lucknow Development Authority against Pushpa before up_rera.

Delay in PossessionDelay Compensation / InterestPromotional Misrepresentation
2
Stage 130/06/2022

for delivery of Judgment/Order

The Tribunal partially allowed the allottee's appeal by modifying the original order to grant interest for the entire delay period (08.12.2013 to 07.01.2019), rejecting the LDA's attempt to exclude time spent in arbitration, and directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement.

3
Stage 222/04/2022

Delay condonation

The Tribunal heard arguments regarding the appellant's challenge to a compensation order, specifically focusing on whether civil disturbances exempt the developer from delay interest and whether the relief granted exceeded the original prayer.

4
Stage 323/03/2022

Delay condonation

The Tribunal directed that the appeal be listed for consideration of a condonation of delay application and to be heard alongside cross-appeal No. 185/2021 on 22.04.2022.

5
Stage 404/03/2022

Further Order

The Tribunal granted the appellant ten days to file a reply to the objections raised by the respondent and scheduled the matter for March 23, 2022.

6
Stage 521/01/2022

Defect Removal

No text available.

7
Stage 621/12/2021

Defect Removal

The Tribunal directed the appellant to complete service steps for the respondent within three days and scheduled the case for further orders on 21.01.2022.

8
Stage 725/11/2021

Defect Removal

No text available.

9
Stage 8Final Ruling Order

Tribunal Order #0901126030802021-30-06-2022

The Tribunal partially allowed the allottee's appeal by modifying the original order to grant interest for the entire delay period (08.12.2013 to 07.01.2019), rejecting the LDA's attempt to exclude time spent in arbitration, and directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement.

10
Stage 9Interim Order

Tribunal Order #0901126030802021-22-04-2022

The Tribunal heard arguments regarding the appellant's challenge to a compensation order, specifically focusing on whether civil disturbances exempt the developer from delay interest and whether the relief granted exceeded the original prayer.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal partially allowed the allottee's appeal by modifying the original order to grant interest for the entire delay period (08.12.2013 to 07.01.2019), rejecting the LDA's attempt to exclude time spent in arbitration, and directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement. Awarded in favor of Partial. Awarded interest rate: SBI's MCLR+1%.

Disposal Winner: PartialInterest Rate: SBI's MCLR+1%Status: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal partially allowed the allottee's appeal by modifying the original order to grant interest for the entire delay period (08.12.2013 to 07.01.2019), rejecting the LDA's attempt to exclude time spent in arbitration, and directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement.

Ruling Awarded To

Partial

Awarded Interest Rate

SBI's MCLR+1%

Interest Period

from 08.12.2013 to 07.01.2019

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 12

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Saurabh Misra

Respondent Advocate(s)

  • Hridesh Srivastava

Official RERA Tribunal Orders (2)

FINAL_ORDEROrder ID: 0901126030802021-30-06-2022

The Tribunal partially allowed the allottee's appeal by modifying the original order to grant interest for the entire delay period (08.12.2013 to 07.01.2019), rejecting the LDA's attempt to exclude time spent in arbitration, and directed the transfer of the promoter's pre-deposited amount to U.P. RERA for disbursement.

INTERIM_ORDEROrder ID: 0901126030802021-22-04-2022

The Tribunal heard arguments regarding the appellant's challenge to a compensation order, specifically focusing on whether civil disturbances exempt the developer from delay interest and whether the relief granted exceeded the original prayer.

TathyaGrid RERA Intelligence AI

Need to research all rulings for a builder?

Extract builder dossiers, check execution status, and draft RERA appeal petitions in minutes using TathyaGrid.

Open AI Workspace →