up_reraStatus: Completed
CASE ID: 0901126030722024

Appellant / Complainant

Prabhat Verma, Anuradha Verma

VS

Respondent

Lucknow Development Authority

Disposal Award

Appellant

TathyaGrid Legal Copilot: Automated procedural intelligence extracted from official RERA tribunal records.
Analyze in Workspace

Legal Issues & Claims Raised

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability

Case Procedural History & Progression Tree

Visual step-by-step tree detailing dispute origin, interim hearings, and final tribunal ruling.

15 Milestones
Filing Phase

Complaint Filing & Dispute Registration

Complaint registered under Case ID 0901126030722024 by Prabhat Verma, Anuradha Verma against Lucknow Development Authority before up_rera.

Delay in PossessionDelay Compensation / InterestJurisdiction & Maintainability
2
Stage 129/08/2025

for delivery of Judgment/Order

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations under Section 18(1) by citing delay or the execution of a conveyance deed.

3
Stage 223/04/2025

Further Hearing

The Tribunal has heard arguments from the counsels for all parties and has reserved the judgment for a later date.

4
Stage 321/04/2025

Further Hearing

No text available.

5
Stage 411/04/2025

Further Hearing

The Tribunal has adjourned the matter and scheduled the appeal for further hearing on April 21, 2025, at 1:30 p.m.

6
Stage 509/04/2025

Further Hearing

The Tribunal has adjourned the appeal to 11.04.2025 for hearing following a joint request from the counsel for both parties.

7
Stage 608/04/2025

Further Hearing

This is a procedural order referring the matter to a previous order passed in Appeal No. D 220/2024.

8
Stage 727/03/2025

Further Hearing

Upon the joint request of both parties, the matter has been adjourned and rescheduled for hearing on April 8, 2025, at 1:30 PM.

9
Stage 820/03/2025

Admission

The Tribunal heard arguments from the appellant's counsel and amicus curiae and scheduled the appeal for further hearing on March 27, 2025.

10
Stage 910/03/2025

For Order

The Tribunal granted a request from the appellant's counsel to adjourn the matter and rescheduled the appeal for hearing on 20.03.2025.

11
Stage 1007/02/2025

For Order

The appeal has been adjourned at the request of the respondent's counsel and is scheduled to be listed again on 10.03.2025.

12
Stage 1116/01/2025

For Order

The Tribunal granted a request from the respondent's counsel to adjourn the appeal to 07.02.2025 and directed that any objections be filed in the interim.

13
Stage 1216/12/2024

Admission

The Tribunal issued a notice to the respondent and outlined the procedural requirements for service of notice and the timeline for filing objections and replies.

14
Stage 13Final Ruling Order

Tribunal Order #0901126030722024-29-08-2025

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations under Section 18(1) by citing delay or the execution of a conveyance deed.

Disposal Phase

Tribunal Disposal & Final Award Ruling

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations under Section 18(1) by citing delay or the execution of a conveyance deed. Awarded in favor of Appellant.

Disposal Winner: AppellantStatus: Completed

Final Tribunal Order & Ruling Verdict Summary

Official Ruling Summary

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations under Section 18(1) by citing delay or the execution of a conveyance deed.

Ruling Awarded To

Appellant

Interest Period

from the date of allotment/agreement till the date of offer of possession

Verified Tribunal DocumentationDownload Official Final Tribunal Order PDF

Statutory Sections Cited (RERA Act 2016)

Section 18(1)Section 3Section 79

Appearing Legal Counsel & Advocates

Appellant Advocate(s)

  • Atul Tripathi

Respondent Advocate(s)

  • Abhishek Khare

Official RERA Tribunal Orders (1)

FINAL_ORDEROrder ID: 0901126030722024-29-08-2025

The Tribunal quashed the Regulatory Authority's orders that had rejected complaints on limitation grounds, ruling that the Limitation Act does not apply to RERA proceedings and that promoters cannot evade statutory interest obligations under Section 18(1) by citing delay or the execution of a conveyance deed.